# BoQ for NITC four research labs

Internet and Intranet · Chapter 5: Designing Internet Systems and Servers

- Asked in: 2072 Asoj, 12 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_8/internet_and_intranet/boq-nitc-research-labs
- Whole chapter: https://www.bctengineer.com/md/semester_8/internet_and_intranet/chapter-5

## Question

NITC building had 4 research labs each having 24 computers. All labs are located at the 1st floor. Each computer is to be connected in the network from NCR located at 2nd floor. Prepare a bill of quantity (BoQ) with necessary network resources required for complete networking. The BoQ must include estimation of all network resources required.

## Short answer

For 96 PCs plus 4 APs, estimate 100 CAT6 drops at 35 m average, giving 3,850 m and 13 boxes. Use 100 faceplates, 5 patch panels, 4 access switches plus 1 PoE switch, and 1 core L3 switch. Assign each lab a /27 subnet from 192.168.10.0/24.

## Answer

#### Assumptions

- 4 labs x 24 computers = 96 computers, all on the 1st floor. The Network Control Room (NCR) is on the 2nd floor, directly above.
- One single-port CAT6 outlet per computer, plus 1 wireless AP per lab (4 drops). Total drops = 96 + 4 = 100.
- Floor height 4 m; horizontal run about 28 m; plus slack: average cable run per drop = 35 m (under the 90 m limit).
- 10% wastage on cable. Cable box = 305 m. Switches are 24-port GE with SFP uplinks. The NCR also needs a router/firewall for the internet link.

#### Layout

```text
 Internet
    |
 [Router/Firewall]            NCR (2nd floor)
    |
 [Core L3 switch]
    |
 [Patch panels x5]--[Switch x5 (4 + 1 PoE)]
    |
    | CAT6 (100 runs, 35 m average)
 ---+---------+---------+---------+---  1st floor
  Lab 1     Lab 2     Lab 3     Lab 4
  24 PC     24 PC     24 PC     24 PC
  + AP      + AP      + AP      + AP
```

#### Quantity estimation

1. Outlets (single-port faceplate with jack): 96 + 4 = **100**.
2. Cable length: 100 x 35 = 3,500 m. With 10% wastage = 3,850 m. Boxes = 3,850 / 305 = 12.6, so **13 boxes**.
3. Patch panel ports = 100. 100 / 24 = 4.2, so **5 patch panels** (24-port).
4. Switches: 96 PC ports / 24 = 4 switches fully used, plus 1 PoE switch for the 4 APs and spare ports = **5 access switches**. One core L3 switch connects them to the router = **1**.
5. Patch cords: user side 2 m = 100; panel to switch 1 m = 100; switch to core 1 m = 5. Total **205**.
6. Rack space: 5 panels (5U) + 5 switches (5U) + core (1U) + router/firewall (1U) + cable managers (4U) + UPS (2U) = 18U, so one 24U or 42U rack.

#### Bill of Quantity

| S.N. | Item | Specification | Qty |
|---|---|---|---|
| 1 | CAT6 UTP cable | 305 m box | 13 boxes |
| 2 | Faceplate + jack | Single-port, CAT6 | 100 |
| 3 | Patch panel | 24-port CAT6 | 5 |
| 4 | Patch cord 2 m | CAT6 | 100 |
| 5 | Patch cord 1 m | CAT6 | 105 |
| 6 | Access switch | 24-port GE + 2 SFP | 4 |
| 7 | PoE switch | 24-port PoE+ | 1 |
| 8 | Core L3 switch | 24-port, SFP+ | 1 |
| 9 | Wireless AP | Dual-band, PoE | 4 |
| 10 | Router / firewall | NAT, DHCP | 1 |
| 11 | Rack | 42U with cable managers | 1 |
| 12 | UPS | 2 kVA | 1 |
| 13 | PVC conduit / trunking | 25 mm | 150 m |
| 14 | Cable ties, labels | | lot |
| 15 | Cable tester | | 1 |

#### IP plan (192.168.10.0/24)

| Network | Subnet | Usable | Gateway |
|---|---|---|---|
| Lab 1 | 192.168.10.0/27 | 30 | .1 |
| Lab 2 | 192.168.10.32/27 | 30 | .33 |
| Lab 3 | 192.168.10.64/27 | 30 | .65 |
| Lab 4 | 192.168.10.96/27 | 30 | .97 |
| Wi-Fi / APs | 192.168.10.128/27 | 30 | .129 |
| Servers / management | 192.168.10.160/27 | 30 | .161 |

Each /27 has 30 usable hosts, enough for 24 PCs and a gateway with spare addresses. The core L3 switch routes between the subnets, and the router provides DHCP (through DHCP relay on the core) and NAT to the internet.

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. How many network outlets (drops) does the NITC BoQ calculate?
   A. 96
   B. 100
   C. 104
   D. 120
   Answer: B. 4 labs x 24 PCs = 96 computers, plus 1 AP per lab (4), giving 100 drops. (Key point: Counting drops)

2. How is the number of CAT6 boxes found?
   A. 100 x 35 m = 3,500 m, add 10% wastage to get 3,850 m, divide by 305 m and round up to 13
   B. 3,500 m divided by 305 m rounded down to 11
   C. 96 x 35 m divided by 100 m per box
   D. 100 x 90 m divided by 305 m
   Answer: A. Wastage is added before dividing by the 305 m box length, and the result 12.6 is rounded up to 13 boxes. (Key point: Cable estimation)

3. Why are 5 patch panels needed?
   A. One per lab plus a spare
   B. 100 ports divided by 24 per panel is 4.2, rounded up to 5
   C. Each switch needs two panels
   D. Each AP needs its own panel
   Answer: B. There are 100 terminated cables and each panel has 24 ports, so 4.2 panels means 5. (Key point: Patch panel count)

4. How are the 205 patch cords made up?
   A. 100 user-side 2 m, 100 panel-to-switch 1 m, and 5 switch-to-core 1 m
   B. 96 + 96 + 13
   C. 200 user-side only
   D. 100 panel-to-switch and 105 switch-to-router
   Answer: A. Each drop needs a 2 m user cord and a 1 m panel-to-switch cord, and each of the 5 access switches needs a 1 m uplink to the core. (Key point: Patch cord total)

5. Why is an extra PoE switch included beyond the four 24-port access switches?
   A. To provide a second core
   B. To power the 4 wireless APs over the cable and give spare uplink ports
   C. To connect the router to the internet
   D. To extend cables beyond 90 m
   Answer: B. Four switches fully serve the 96 PCs; one PoE switch powers the 4 APs. (Key point: Why a separate PoE switch)

## Related in Internet and Intranet

- [BOQ for DOECE four computer labs](https://www.bctengineer.com/question.md?key=semester_8%2Finternet_and_intranet%3Aboq-doece-four-labs) — Internet and Intranet, chapter 5
- [BoQ for IOE ICT building six labs](https://www.bctengineer.com/question.md?key=semester_8%2Finternet_and_intranet%3Aboq-ioe-ict-six-labs) — Internet and Intranet, chapter 5

## Related in other subjects

- [Prepare AOC, BOQ and summary of cost](https://www.bctengineer.com/question.md?key=semester_7%2Festimating_and_costing%3Aaoc-boq-summary-numerical) — Estimating and Costing, chapter 2