title: "400 kV lines: configuration, V-string, earth wires"
subject: "Transmission and Distribution System Design"
chapter: 4
key: "semester_8/transmission_and_distribution_system_design:justify-400kv-config-vstring-earthwire"
source: https://www.bctengineer.com/q/semester_8/transmission_and_distribution_system_design/justify-400kv-config-vstring-earthwire
site: BCT Engineering
---

# 400 kV lines: configuration, V-string, earth wires

Transmission and Distribution System Design · Chapter 4: Conductor and Support Selection

- Asked in: 2067 Chaitra (old course), 8 marks
- Answer checked by Claude Opus 5.5 (high effort) on 2026-10-14
- Page: https://www.bctengineer.com/q/semester_8/transmission_and_distribution_system_design/justify-400kv-config-vstring-earthwire
- Whole chapter: https://www.bctengineer.com/md/semester_8/transmission_and_distribution_system_design/chapter-4

## Question

For a 400 kV and above voltages transmission line, justify the following facts: i) Horizontal conductor configuration is a general choice. ii) V-type insulator string is preferred. iii) Double earth wire is selected.

## Short answer

Horizontal configuration lowers tower height and overturning moment. V‑strings prevent wind swing, reducing phase spacing and right‑of‑way. Double earth wires give a small shielding angle for all phases and lower tower‑top potential to reduce back‑flashover.

## Answer

At 400 kV and above, phase-to-tower clearances (about 3–3.5 m), insulator strings (about 4 m) and conductor bundles are large. This changes the best layout of the tower.

#### i) Horizontal conductor configuration
- With a vertical or triangular layout, each phase needs its own cross arm and about 8–9 m of vertical spacing. The tower would become very tall, roughly 50–60 m, giving a large overturning moment and a heavy, costly tower.
- A **horizontal** layout puts all three phases at one level. The tower is the **lowest possible**, which reduces bending moment, tower weight, foundation cost and wind load.
- A lower tower is also struck by lightning less often.
- A wide right-of-way is needed, but at 400 kV it is wide anyway because of the clearances. Horizontal-configuration towers (waist type or portal/H-frame) are therefore the common choice.

#### ii) V-type insulator string
- An I-string can swing under wind, up to 45° or more. The cross arm must then be long enough for the swung conductor to keep its clearance from the tower: $X = a + l\sin\theta$. At 400 kV, with $l \approx 4$ m, this is very long.
- A **V-string** has two legs at about 90° to each other, so the conductor **cannot swing**. The phase spacing and window size can be reduced. The tower top becomes narrower and lighter, and the **right-of-way is reduced**.
- The two legs share the load, so a V-string can carry heavy quad-bundle conductors and gives better mechanical security.
- It also has better self-cleaning and pollution performance, because water runs off the inclined discs.

#### iii) Double earth wire
- In a horizontal configuration the outer phases are 10–12 m from the centre line. A single central earth wire would give a shielding angle far above the required 20–30°, and the outer phases would suffer **shielding failures**.
- Two earth wires, placed above or near the outer phases, give a small (even negative) **shielding angle** to all three phases.
- Two parallel earth wires also lower the surge impedance of the earth path and the tower-top potential. This reduces back-flashover, which matters because 400 kV outages are costly. They also share fault current and can carry OPGW for communication.

```text
     E                       E      earth wires
      \                     /
   ----\--------+----------/----   cross arm
       V        V          V       V-strings
      (A)      (B)        (C)      horizontal phases
                |
               tower
```

## Check yourself

The answer's key points as multiple-choice questions, with the correct option and why.

1. Why is a horizontal conductor configuration general at 400 kV and above?
   A. It gives the lowest tower, reducing moment, weight and foundation cost
   B. It needs a narrower right-of-way
   C. It reduces corona
   D. It removes the need for earth wires
   Answer: A. All phases at one level give the lowest tower, though a wide right-of-way is needed. (Key point: Horizontal configuration)

2. Why is a V-type insulator string preferred?
   A. It increases conductor swing
   B. It uses fewer discs
   C. It raises the phase spacing
   D. It prevents conductor swing, so cross arm and phase spacing can be reduced
   Answer: D. The two legs at about 90° hold the conductor, reducing tower width and right-of-way. (Key point: V-string purpose)

3. Why does an I-string need a long cross arm at 400 kV?
   A. It swings under wind, so X = a + l sin(theta) must keep clearance, and l is about 4 m
   B. It carries less load
   C. The earth wire is lower
   D. Its discs are heavier
   Answer: A. The swung string brings the conductor closer to the tower, so the cross arm must be long. (Key point: I-string problem)

4. Why are two earth wires used with horizontal configuration?
   A. To raise the voltage
   B. A single central wire gives a large shielding angle for outer phases (10-12 m away), causing shielding failure
   C. To reduce the tower height
   D. To increase sag
   Answer: B. Two wires give small shielding angles to all phases and lower back-flashover and surge impedance. (Key point: Double earth wire)

## Related in Transmission and Distribution System Design

- [T/F: double earth wire for 400 kV single circuit](https://www.bctengineer.com/question.md?key=semester_8%2Ftransmission_and_distribution_system_design%3Atf-400kv-single-circuit-double-earth) — Transmission and Distribution System Design, chapter 3
- [T/F: conductor configuration for 400 kV lines](https://www.bctengineer.com/question.md?key=semester_8%2Ftransmission_and_distribution_system_design%3Atf-vertical-configuration-400kv) — Transmission and Distribution System Design, chapter 4, asked 2×
- [Tower dimensions for 220 kV double circuit line](https://www.bctengineer.com/question.md?key=semester_8%2Ftransmission_and_distribution_system_design%3Atower-dimensions-220kv-double-circuit) — Transmission and Distribution System Design, chapter 4, asked 2×
- [T/F: V-type string for 400 kV lines](https://www.bctengineer.com/question.md?key=semester_8%2Ftransmission_and_distribution_system_design%3Atf-v-string-400kv-mechanical) — Transmission and Distribution System Design, chapter 3
- [Air clearances for 132 kV double circuit line](https://www.bctengineer.com/question.md?key=semester_8%2Ftransmission_and_distribution_system_design%3Aair-clearance-132kv-double-circuit) — Transmission and Distribution System Design, chapter 4
- [Air clearances for 220 kV double circuit line](https://www.bctengineer.com/question.md?key=semester_8%2Ftransmission_and_distribution_system_design%3Aair-clearance-220kv-double-circuit) — Transmission and Distribution System Design, chapter 4

## Related in other subjects

- [400 kV line with 3-conductor bundles: reactances and VAR](https://www.bctengineer.com/question.md?key=semester_4%2Fpower_system_analysis_i%3Atriple-bundle-400kv-reactances) — Power System Analysis I, chapter 4, asked 3×
- [Tower top potential and insulator string voltage](https://www.bctengineer.com/question.md?key=semester_8%2Fhigh_voltage_engineering%3Atower-top-potential-insulator-voltage) — High Voltage Engineering, chapter 3, asked 2×
- [RI levels of 400 kV line at 1 MHz](https://www.bctengineer.com/question.md?key=semester_8%2Fhigh_voltage_engineering%3Ari-400kv-cigre-1mhz) — High Voltage Engineering, chapter 5
- [Capacitance matrix of 400 kV bundled line](https://www.bctengineer.com/question.md?key=semester_8%2Fhigh_voltage_engineering%3Acapacitance-matrix-400kv-15m) — High Voltage Engineering, chapter 5, asked 2×