- 2063 Baisakh (old course) · 4+4 marks
Fold, fault, joint, thrust in tunnelling
Short answer
Fold: bent rock layers; anticline crests are fractured causing roof falls, syncline troughs have high pressure and water; tunnel should cross fold axis at high angle. Fault: crushed zone causes collapse, squeezing, water inflow; cross at right angle, probe and grout. Joint: cause overbreak, wedge falls, seepage; support with bolts and shotcrete. Thrust: wide shear zone with high squeezing and water inflow, requiring heavy support.
Define fold, fault, joint and thrust. Describe the engineering significance of each of the above mentioned geological structures in tunnelling.
Definitions
- Fold: a bend or wavy curvature of originally flat rock layers caused by compression, such as an anticline or syncline.
- Fault: a fracture in the rock along which the two blocks have displaced relative to each other.
- Joint: a fracture in the rock along which there has been no (or negligible) displacement.
- Thrust: a low-angle (<45°) reverse fault where the hanging wall moves up over the foot wall, bringing older rocks over younger.
Significance in tunnelling
| Structure | Significance in tunnelling |
|---|---|
| Fold | Crest of an anticline is loosened and fractured (roof falls); the trough of a syncline has high rock pressure and water collection. The tunnel axis should cross the fold axis at a high angle and avoid running along the axis in the crest or trough. Limb dip decides the support type. |
| Fault | Crushed zone (breccia, gouge) gives roof collapse, squeezing and heavy support. Faults carry water, giving sudden inflow and flooding. Tunnels should cross faults at a right angle, and the active fault may displace the lining. Probe drilling and grouting are used. |
| Joint | Cause overbreak, wedge falls and water seepage. Tunnels parallel to the main joint set are less stable; rock bolts, shotcrete and grouting are used for support. |
| Thrust | A wide shear zone of crushed, sheared rock with sheared clay, very high squeezing and high water inflow; for example, tunnels in the Himalaya crossing MCT and MBT face heavy support and delays. |
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Engineering significance of joint and fault · Engineering Geology I, chapter 5 · asked 2×
- What is joint; engineering significance of joint and fault · Engineering Geology I, chapter 5 · asked 2×
- Fold, fault and joint; attitude · Engineering Geology I, chapter 5
- Engineering significance of fold · Engineering Geology I, chapter 5
- Engineering significance of fault · Engineering Geology I, chapter 5 · asked 6×
- Importance of fold; define thrust · Engineering Geology I, chapter 5 · asked 2×
- Geological documentation in tunnelling · Engineering Geology II, chapter 4 · asked 6×
- Engineering geological problems of Siwalik zone · Engineering Geology II, chapter 2 · asked 4×
- Control system and its significance in engineering · Control Systems, chapter 1