- 2069 Chaitra · 8 marks
Area by coordinate method from offsets
Short answer
Take the chain line as x-axis and form a closed polygon with the chain ends and offset endpoints. Coordinate area = ½|Σ(x_i y_{i+1} − x_{i+1} y_i)| = 38.479 m².
Calculate the area by the coordinate method from the following perpendicular offsets taken from a chain line to a boundary.
| Chainage (m) | 0.00 | 3.75 | 6.50 | 11.30 | 16.45 |
|---|---|---|---|---|---|
| Offset (m) | 1.45 | 2.50 | 2.95 | 2.10 | 2.35 |
Method. The chain line is taken as the x-axis and the first offset position as the origin. The ends of the offsets and the two chain-line corners form a closed polygon whose area is found from its coordinates:
Coordinates (taken in order round the area)
| Point | (m) | (m) |
|---|---|---|
| Chain start | 0.00 | 0.00 |
| Chain end | 16.45 | 0.00 |
| offset 5 | 16.45 | 2.35 |
| offset 4 | 11.30 | 2.10 |
| offset 3 | 6.50 | 2.95 |
| offset 2 | 3.75 | 2.50 |
| offset 1 | 0.00 | 1.45 |
Calculation
| Pair | Difference | ||
|---|---|---|---|
| P1→P2 | 0.0000 | 0.0000 | 0.0000 |
| P2→P3 | 38.6575 | 0.0000 | 38.6575 |
| P3→P4 | 34.5450 | 26.5550 | 7.9900 |
| P4→P5 | 33.3350 | 13.6500 | 19.6850 |
| P5→P6 | 16.2500 | 11.0625 | 5.1875 |
| P6→P7 | 5.4375 | 0.0000 | 5.4375 |
| P7→P1 | 0.0000 | 0.0000 | 0.0000 |
| Sum | 76.9575 |
Check (trapezoidal strips): the four strips give 7.4063 + 7.4938 + 12.1200 + 11.4588 = 38.4788 m².
Answer: area = 38.479 m².
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Offsets area: trapezoidal, Simpson, coordinate · Surveying I, chapter 9
- Area from perpendicular offsets to a hedge · Surveying I, chapter 9
- Area between boundary, offsets and base line · Surveying I, chapter 9
- Area enclosed by chain line and hedge · Surveying I, chapter 9
- Area from offsets, 10 m interval · Surveying I, chapter 9
- Area from eight offsets at 20 m interval · Surveying I, chapter 9 · asked 2×
- AVL tree for 10, 20, 30, 35, 50, ... · Data Structure and Algorithm, chapter 6
- AVL tree for 10 20 30 50 45 40 8 5 3 · Data Structure and Algorithm, chapter 6
- Design: 250 m head plant, 35 km line · Power Plant Design, chapter 4 · asked 12×
- EVA; BCWS 9,50,000, BCWP 8,00,000, ACWP 10,00,000 · Project Engineering, chapter 4