Short answer

Stations must be intervisible, form well-conditioned triangles, and keep lines near details for short offsets; a long base line on level ground with check lines is essential. A well-conditioned triangle (angles 30–120 degrees) minimizes plotting error because a small measurement error causes large point displacement if intersection angle is small (displacement is about error/sinθ).

What factors should be considered in selecting stations as well as chain lines of a chain survey? Why is it necessary to use a well-conditioned triangle?

Factors in selecting stations and chain lines

  1. Intervisibility. Stations should be visible from each other so that lines can be ranged and chained easily.
  2. Well-conditioned triangles. The lines should make triangles with all angles between 30∘30^\circ and 120∘120^\circ.
  3. Base line. Choose the longest line on level ground through the middle of the area; it carries the main framework.
  4. Short offsets. Lines should pass close to the details so that offsets are not longer than 15 m.
  5. Minimum number of stations and lines, to reduce work and errors.
  6. Ground. Avoid steep slopes, ponds, buildings and thick bushes on lines.
  7. Check and tie lines must be provided.
  8. Stations should be on firm, permanent ground and tied to objects.

Why a well-conditioned triangle is necessary

A triangle is plotted from the lengths of its three sides by intersecting arcs. If an angle is very small or very large (an ill-conditioned triangle), the arcs intersect at a flat angle, and a small error in a measured length moves the plotted point by a large amount:

displacement≈δsin⁡θ\text{displacement} \approx \frac{\delta}{\sin\theta}

where δ\delta is the error in the side and θ\theta the intersection angle. For θ=15∘\theta = 15^\circ, an error of 1 mm shifts the point 3.9 mm; for θ=60∘\theta = 60^\circ only 1.15 mm. An equilateral triangle is the best shape; angles from 30∘30^\circ to 120∘120^\circ are acceptable. This keeps the plotting error small and the framework accurate.