- Practice · 6 marks
Product cycle and manufacturing flows
Short answer
Product cycle stages are market need, design, process planning, production, distribution/use/service, and disposal/recycling. Material flow is physical movement through purchasing, storage, processing, assembly, inspection, packing and dispatch. Information flow carries orders, drawings, bills of material, schedules and reports both ways, and must be synchronised with material flow.
Explain the product cycle from market need to disposal. Distinguish between the material flow and the information flow in a manufacturing system, giving the main activities in each.
The product cycle is the sequence of stages a product passes through from the identification of a customer need to its final disposal or recycling. Manufacturing is only one stage of it, but decisions taken in the design stage fix most of the cost of the product.
Stages of the product cycle
Market need -> Concept design -> Detail design
^ |
| v
Disposal/ <- Use & service <- Manufacture <- Process
recycling & assembly planning
- Market need and specification - customer requirement, competitors, target cost and volume.
- Design - concept, analysis, material selection, drawings, prototype and testing (design for manufacture and assembly).
- Process planning - choice of processes, machines, tooling, sequence of operations, inspection plan.
- Production - fabrication of parts, assembly, quality control, packing.
- Distribution, use and service - sales, maintenance, spare parts, warranty.
- Disposal or recycling - reuse of materials, safe disposal.
Material flow and information flow
The material flow is the physical movement and transformation of raw material into the finished product. The information flow is the stream of data that plans, controls and records that movement.
| Basis | Material flow | Information flow |
|---|---|---|
| Nature | Physical items | Data and documents |
| Direction | Supplier to customer | Both ways: orders down, feedback up |
| Activities | Purchase, storage, processing, handling, assembly, inspection, packing, dispatch | Customer order, drawings, bill of materials, process plan, schedule, work order, inspection reports |
| Tools | Conveyors, AGVs, fixtures, stores | MRP, ERP, CAD/CAM, barcode, CNC programs |
| Aim | Minimum handling and waiting | Right item, right time, right quantity |
The two flows must be synchronised: a work order (information) releases material from the store, and the completion record (information) updates the stock. Poor information flow produces idle machines, excess work-in-process and late deliveries even when the machines are good.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Flow curve constants K and n · Manufacturing and Production Processes, chapter 2
- Lathe operations, taper turning and turning calculations · Manufacturing and Production Processes, chapter 7
- Residual stresses: causes, effects, relief · Manufacturing and Production Processes, chapter 3
- Powder metallurgy process and applications · Manufacturing and Production Processes, chapter 4
- NC and CNC machines: elements and justification · Manufacturing and Production Processes, chapter 9
- Drill jig and fixture design considerations · Manufacturing and Production Processes, chapter 10
- Project life cycle phases and activities · Project Engineering, chapter 1 · asked 5×
- Product versus project life cycle · ICT Project Management, chapter 4
- Manufacturing execution system and automation · Computer Aided Design, chapter 6
- Fair market value of Tata Sipradi showroom · Construction Management, chapter 13
All Manufacturing and Production Processes chapter 1 questions →