Casting and curing temperature; concreting in Kathmandu

Short answer

High temperature increases early strength but reduces long-term strength due to non-uniform gel; low temperature gives higher ultimate strength but slows early gain. In Kathmandu, cast in spring/autumn; in winter use warm water, cover, and delay form removal; in summer avoid hot/dry winds, shade, and cure continuously for 7–10 days.

Explain the influence of casting and curing temperatures on concrete strength and suggest the appropriate method of concreting in Kathmandu.

Casting and curing temperature change the speed of hydration and the final structure of the gel. A high temperature gives high early strength but a lower 28-day and long-term strength (non-uniform gel, coarse pores, drying cracks). A low temperature slows early strength but improves later strength, as the gel forms more densely; near freezing, hydration almost stops and fresh concrete can be damaged by ice.

Concreting in Kathmandu

Kathmandu valley has a temperate climate: mild to warm summers (up to about 30 °C) and cool winters (night temperature 0 to 5 °C in December to January) with fog and little rain in winter. The temperature is mostly favourable, but special care is needed in winter and in the pre-monsoon dry period.

  1. Season: prefer casting in spring and autumn, between 10 and 30 °C; avoid pouring in the cold early morning of Poush to Magh, or heavy monsoon rain unless protected.
  2. Cement: OPC 43 or PPC (Nepal Standard), with fresh stock; PPC is acceptable with extended curing. For durable work follow the minimum cement content and maximum w/c of IS 456 Table 5 for the exposure (mild or moderate: w/c 0.50 to 0.55).
  3. Winter: keep the concrete at 5 °C or higher at placing (IS 456, Cl. 14.1); use warm mixing water, cover with plastic and straw/jute at night, delay formwork stripping, avoid casting if frost is expected.
  4. Summer (dry spells): cast in early morning or evening, wet the forms, shade, and prevent plastic shrinkage cracking (IS 456, Cl. 14.1).
  5. Curing: keep moist for at least 7 days for OPC and 10 days for PPC (IS 456, Cl. 13.5.1) with ponding or wet hessian, and use a curing compound where water is scarce.
  6. Mix: use a water-reducing admixture, keep w/c low, compact properly, and cast cubes cured under site conditions for stripping decisions.

Thus normal procedures with attention to cold-night protection and proper curing are enough for Kathmandu.