DOE mix design for M25 concrete (numerical)

Short answer

DoE method, w/c 0.50, water 205 kg/m³. Mix per m³: cement 410 kg, water 205 kg, FA 706 kg, CA 1059 kg. For 2 m³: cement 820 kg, water 410 L, FA 1412 kg, CA 2118 kg.

Design the mix proportion for concrete with the help of the following given data: concrete grade M 25; maximum size of aggregate 25 mm; specific gravity of C.A. 2.7; specific gravity of F.A. 2.6; degree of exposure moderate; fineness modulus of F.A. 3.00; method of design: DOE method. Based on the mix ratio obtained, calculate the quantity of ingredients of concrete for 2 m3^3 concrete production. (Assume all necessary relevant data)

Method: DoE (BRE 1988).

Data: M25; maximum size 25 mm; GCA=2.7G_{CA} = 2.7, GFA=2.6G_{FA} = 2.6; moderate exposure; FM of FA = 3.0 (zone 2/1 sand).

Assumptions: OPC 43, crushed aggregate, medium workability (slump 30-60 mm), s=4s = 4 MPa (IS 456 Table 8 for M25), cement SG 3.15, no admixture.

Step 1: Target mean strength

fm=fck+1.64s=25+1.64×4=31.6 MPaf_m = f_{ck} + 1.64 s = 25 + 1.64 \times 4 = 31.6\ \text{MPa}

Step 2: w/c ratio. From Table 2 (49 MPa at w/c 0.5 for crushed aggregate with OPC at 28 days) and Fig 1, 31.6 MPa corresponds to w/c ≈\approx 0.7. Durability (IS 456 Table 5, moderate exposure, RCC): maximum w/c = 0.50, minimum cement 300 kg/m3^3. So adopt w/c = 0.50.

Step 3: Free water (DoE Table 3, crushed aggregate, 30-60 mm slump): 20 mm gives 210 and 40 mm gives 190 kg/m3^3; interpolating for 25 mm gives 205 kg/m3^3.

Step 4: Cement = 205/0.50=410205/0.50 = 410 kg/m3^3 (above 300 and below 550 kg/m3^3).

Step 5: Wet density (Fig 3, water 205, combined aggregate SG about 2.65) ≈\approx 2380 kg/m3^3; total aggregate = 2380−205−410=17652380 - 205 - 410 = 1765 kg/m3^3.

Step 6: Fine aggregate proportion (Fig 4, size 25 mm, 30-60 mm slump, w/c 0.5, coarse sand) ≈\approx 40%:

FA=0.40×1765=706 kg,CA=1765−706=1059 kgFA = 0.40 \times 1765 = 706\ \text{kg},\quad CA = 1765 - 706 = 1059\ \text{kg}

Volume check: 0.205+410/3150+706/2600+1059/2700=0.9990.205 + 410/3150 + 706/2600 + 1059/2700 = 0.999 m3^3 - satisfactory.

Mix per m3^3: cement 410 kg : water 205 kg : FA 706 kg : CA 1059 kg, ratio 1 : 1.72 : 2.58, w/c = 0.50.

Quantities for 2 m3^3

MaterialQuantity (kg)
Cement820
Water410 (litres)
Fine aggregate1412
Coarse aggregate2118

Answer: for 2 m3^3, cement 820 kg (about 16.4, i.e. 17 bags of 50 kg), water 410 L, FA 1412 kg, CA 2118 kg. Correct for moisture and absorption at site and verify by a trial mix.