Spiral model of software development

Short answer

The spiral model iteratively goes through objective setting, risk analysis, development, and review in each loop. It combines waterfall phases with prototyping and explicit risk handling, producing increasingly complete versions, suitable for large high-risk projects.

Spiral model of software development combines the elements of both waterfall and prototyping model. Explain the process of software development using spiral model.

The spiral model (Barry Boehm) is a risk-driven, iterative process. It combines the stepwise, controlled phases of the waterfall model with the iterative prototyping model, and adds explicit risk analysis at every loop. The project moves outward through a spiral; each loop is a phase (concept, requirements, design, implementation) and produces a more complete version.

 +---------------------+---------------------+
 | 1 Objectives,       | 2 Risk analysis,    |
 |   alternatives      |   prototype         |
 +---------------------+---------------------+
 | 4 Plan next loop,   | 3 Develop and       |
 |   customer review   |   test              |
 +---------------------+---------------------+
   Loops go outward: concept -> requirements
   -> design -> code/test -> release

Process (each loop has four quadrants)

  1. Determine objectives, alternatives and constraints: the requirements for this loop are set (performance, functionality, cost), the alternative solutions are listed.
  2. Evaluate alternatives and identify/resolve risks: risks (technical, schedule, cost, requirement uncertainty) are analysed; prototypes, simulation or benchmarks are built to reduce them. If a risk is too high, the project may stop.
  3. Develop and verify the next level of product: design, coding, and testing for the loop (e.g. concept of operation, then requirements, then design, then the code, then acceptance), using waterfall for that cycle.
  4. Plan the next iteration: the customer reviews the result and the plan for the next loop (and budget) is prepared.

The first loops produce the concept and prototype; later loops produce the detailed design, code and tests, until the final system is delivered. The radius of the spiral represents cumulative cost, and the angle the progress.

Advantages: risk handled early, flexible for changes, customer feedback each loop, suits large and high-risk projects. Disadvantages: needs risk-analysis expertise, costly, complex to manage, not suitable for small projects.