A foundation is the lowest part of a structure transferring loads to the ground; types include shallow (spread, strip, raft) and deep (pile, pier, well). Settlement is caused by consolidation, weak or non-uniform soil, water table changes, overloading, adjacent works and earthquakes. Treatment includes underpinning, enlarging footings, grouting, drainage, load reduction, piles/micropiles and crack repair.
Define foundation with its types. What are the causes of foundation settlement and how can we provide treatment for foundation settlement?
Foundation
A foundation is the lowest part of a structure, in direct contact with the ground, which transfers the loads of the structure safely to the soil.
Types
- Shallow foundations: spread (isolated) footing, strip (wall) footing, combined footing, strap footing, raft (mat) foundation, grillage.
- Deep foundations: pile foundation, pier foundation, well (caisson) foundation.
Shallow: [__|__] Deep: | | | piles
---------------------- weak soil
===hard layer===
Causes of foundation settlement
- Consolidation of compressible clay and silt layers under load.
- Weak, loose or filled soil and poor compaction.
- Non-uniform soil strata, giving differential settlement.
- Lowering of ground water table or seasonal shrinkage and swelling of clay.
- Overloading or unequal loading of foundation.
- Adjacent excavation and construction, and vibrations.
- Tree roots drawing moisture.
- Loss of soil by erosion or leakage, and underground voids.
- Earthquake causing densification and liquefaction.
- Faulty design or construction: footing too small or shallow.
Treatment of settlement
- Underpinning: Pit method, pile method, or by extending the footings deeper to a firm stratum.
- Enlarging the foundation to spread the load.
- Soil improvement: Grouting (cement, chemical), compaction grouting, jet grouting.
- Drainage: Control surface and ground water, repair leaking pipes.
- Reducing the load, or tying the structure with beams.
- Pile or micropile supporting under existing footing.
- Removal of trees, or root barriers.
- Repair of cracks after settlement is stabilised.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Foundation settlement causes and underpinning · Building Technology, chapter 2
- Foundation settlement, effects, black cotton soil · Building Technology, chapter 2
- Causes of foundation failure · Building Technology, chapter 2 · asked 2×
- Treatment processes, impurities removal, settlement · Water Supply Engineering, chapter 6 · asked 2×
- Foundation treatment before gravity dam construction · Hydropower Engineering, chapter 4
- Proportioning footings for uniform settlement · Foundation Engineering, chapter 6 · asked 2×
- Clay 10 m, 2.54 cm sample, half settlement · Soil Mechanics, chapter 9