Techniques: epoxy injection for cracks; RCC, steel or FRP jacketing of beams and columns; adding shear walls or steel bracing; foundation widening; ferrocement plaster with cross-ties; inserting lintel, sill and roof bands; RC topping for rigid diaphragm; and removing heavy parapets.

Explain the techniques of retrofitting (seismic retrofitting) of a building.

Retrofitting is the strengthening or modification of an existing building so that it can resist earthquake forces better than it was originally designed to. It improves strength, stiffness, ductility and load path of the existing structure without rebuilding it.

Techniques of seismic retrofitting

1. Local repair (member-level)

Fill cracks by epoxy or cement grout injection, replace crushed concrete or broken bricks, and replace corroded bars.

2. Jacketing of members

  • RCC jacket: extra concrete (min. 75-100 mm) with new longitudinal bars and closely spaced ties is cast around a column or beam.
  • Steel jacket: steel plates or angles with battens are wrapped around the member and the gap is grouted.
  • FRP wrapping: carbon or glass fibre sheets are bonded to give confinement.

3. Adding shear walls or bracing

New RC shear walls, infill walls or steel X-bracing are added in frames to increase lateral stiffness and strength.

4. Strengthening of foundation

Widening of footings, adding tie beams or underpinning if foundation is weak.

5. Strengthening of masonry

Ferrocement or wire mesh plastering on both faces, tying with cross-links; inserting RC bands at plinth, lintel and roof levels; vertical bars at corners and jambs; grouting of cracks; stitching of cracks.

6. Improving connections and diaphragm

Anchoring roof/floor to walls, tying walls with steel straps, converting flexible floors to rigid diaphragms by an RC topping.

7. Base isolation and energy dissipation

Isolators or dampers are placed to reduce earthquake force transfer (costly; used for important buildings).

8. Reducing weight or irregularity

Removing heavy parapets, water tanks, or upper storeys; adding walls to remove soft storey.

Choice of technique depends on the type of building (masonry or RCC), condition survey results (visual and NDT), the expected earthquake level, cost, and working conditions (occupied building or not).