- 2066 Jestha (old course) · 4+6 marks
Why temporary construction; single and double scaffolding
Short answer
Temporary construction provides safe height access, supports walls, shapes concrete, and aids deep work. Single scaffolding has one row of standards 1.2-1.5 m from wall, putlogs fixed in wall holes; used for brickwork. Double scaffolding has two rows, putlogs on both ledgers, no wall holes; used for stone masonry and heavy work.
Why temporary construction is necessary in building construction? Differentiate between single and double scaffolding with constructional details.
Why temporary construction is necessary
- Gives workers and materials a safe, stable platform at height.
- Supports weak walls and trenches during work.
- Provides the shape for concrete until it hardens.
- Allows work on deep foundations and repair of old structures.
- Increases safety, speed and quality of work.
Single and double scaffolding
| Point | Single (brick layer's) | Double (mason's) |
|---|---|---|
| Standards | One row, 1.2-1.5 m from wall | Two rows: 0.2-0.3 m and 1.2-1.5 m from wall |
| Putlogs | One end in wall, other on ledger | Both ends on ledgers, not in wall |
| Hole in wall | Needed | Not needed |
| Used for | Brick masonry, plastering | Stone masonry, heavy work |
| Strength | Less rigid | More rigid, stronger |
| Cost | Cheaper | More expensive |
SINGLE DOUBLE
wall |__ledger__ wall | ledger ledger
wall |--putlog (in wall) wall |==putlog on both==|
wall | standard wall | std std
wall | standard wall | std std
Constructional details: standards are fixed on sole plates, ledgers are lashed or clamped at 1.2-1.8 m height, braces (diagonal) are provided on the face and cross braces for stability, boards 40 mm thick are fixed on the putlogs, and guard rails and toe boards are provided.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Double and cantilever scaffolding · Building Technology, chapter 8
- Types of temporary construction · Building Technology, chapter 8 · asked 2×
- Temporary construction, types and requirements · Building Technology, chapter 8
- Types of temporary construction (list) · Building Technology, chapter 8
- Single, double, multiple timber roofs; king post truss · Building Technology, chapter 4 · asked 2×
- Roof covering; double and triple roofs · Building Technology, chapter 4
- Polymers in building construction · Civil Engineering Materials, chapter 10 · asked 2×
- Building near river bank; stop construction? · Engineering Professional Practice, chapter 7
- Single and double handshaking · Microprocessor, chapter 4
- Single vs double earth wire selection · Transmission and Distribution System Design, chapter 3