Tile drain spacing, Biratnagar rainfall

Short answer

Donnan's formula: K=1×10⁻⁴ m/s, q=2% of 2000 mm in 48 h =2.315×10⁻⁷ m/s, a=12−2=10 m, b=12−1.5=10.5 m. Spacing S ≈133.1 m (say 133 m).

The annual rainfall in Biratnagar is 2000 mm. Find the spacing of sub-surface drains if 2% of average annual rainfall is to be drained in 2 days. Given: Depth of impervious stratum from the top of soil surface = 12 m; Position of drain is 2 m below the top soil surface and the depth of highest position of water table below the top soil surface = 1.5 m; Permeability, K = 1 × 10⁻⁴ m/s.

Tile drain spacing is found from Donnan's (Dupuit–Forchheimer) formula for steady flow towards parallel drains over an impervious layer:

S=4K (b2−a2)qS=\sqrt{\frac{4K\,(b^2-a^2)}{q}}

where SS = spacing, KK = permeability, qq = drainage rate (discharge per unit area), bb = height of the water table above the impervious layer at the mid-point, aa = height of the drain above the impervious layer.

Data

  • Depth of impervious layer = 12 m, depth of drain = 2 m, depth of highest water table = 1.5 m (all below ground)
  • KK = 0.01 cm/s = 0.0001 m/s
  • Rainfall 2000 mm; 2 % to be drained in 48 hours

Step 1: Drainage rate

q=2100×20001000 m/(48×3600 s)=2.315×10−7 m/sq = \frac{2}{100}\times\frac{2000}{1000}\ \text{m} \Big/ (48\times3600\ \text{s}) = 2.315\times10^{-7}\ \text{m/s}

Step 2: Heights above the impervious layer

a=12−2=10 mb=12−1.5=10.5 m\begin{aligned} a &= 12-2 = 10\ \text{m} \\ b &= 12-1.5 = 10.5\ \text{m} \end{aligned}

Step 3: Spacing

S2=4×0.0001×(10.52−102)2.315×10−7=4×0.0001×10.252.315×10−7=17712 m2S=133.1 m\begin{aligned} S^2 &= \frac{4\times0.0001\times(10.5^2-10^2)}{2.315\times10^{-7}} \\ &= \frac{4\times0.0001\times10.25}{2.315\times10^{-7}} = 17712\ \text{m}^2 \\ S &= 133.1\ \text{m} \end{aligned}

Here KK = 1 × 10⁻⁴ m/s = 0.01 cm/s, and 2 % of 2000 mm = 40 mm is drained in 2 days = 48 h.

Answer: spacing of the tile drains ≈ 133.1 m (say 133 m).