- Asked 2/34
- 2075 Baisakh
- 2064 Shrawan (old course) · 8 marks
Surface water drainage in hill roads
Short answer
A catch drain above the cut intercepts hillside runoff, which is led to a side drain and then through culverts across the road. Downstream chutes discharge water into natural streams. Special problems include high-velocity scour, sediment blockage, limited bench space, and water-triggered landslides.
Explain with sketches how the surface water is collected and disposed off in hill roads. What are the special problems in drainage of surface water in hill roads?
How surface water is collected and disposed of
Rain falling on the hill above the road and on the carriageway is collected before it can enter the road structure and then carried across or away from it.
- Catch water drain (uphill, 5-10 m above the cut) intercepts the water from the upper hillside and leads it to a natural stream or cross-drain.
- Side drain (V or trapezoidal, lined) along the hill-side edge of the road collects water from the cut slope and the carriageway (camber 2.5-3% towards the hill, or crown with cross-fall).
- Cross drainage - culverts and small bridges take the water of the side and catch drains across the road at close intervals (about 50-100 m or less, and at all natural nallahs).
- Outlet - the culvert outlet is connected to a chute/cascade, drop wall, or stilling basin to discharge into the natural gully without scouring the fill slope.
- Valley side - berms and kerbs on high fills guide water to outlets; the road surface is kept sealed.
UPHILL ~~~~~
catch drain =====>--+
\ |
cut slope v
----side drain--> culvert ---> chute
=======road======= \
fill slope \__ stream
Special problems of surface-water drainage in hill roads
- Steep slopes give high velocity and scouring of drains, fill slopes and outlets; lining and drop structures are needed.
- Concentrated flow and heavy rainfall in short time; many natural streams and gullies to cross.
- Water entering cracks and cut faces causes landslides, slips and erosion.
- Large sediment/debris load blocks drains and culverts; frequent cleaning is needed.
- Limited space for drains on narrow benches; difficult disposal because no place to discharge safely.
- Snow melt and springs add flow in cold areas.
- The cross-drainage works are many, costly and difficult to build on steep terrain.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Special structures in hill roads · Transportation Engineering I, chapter 5
- Design and construction problems of hill roads · Transportation Engineering I, chapter 5 · asked 11×
- Catch water drains in hill roads · Transportation Engineering I, chapter 5 · asked 2×
- Collection and disposal of surface water · Transportation Engineering I, chapter 4 · asked 2×
- Special considerations in hill road design · Transportation Engineering I, chapter 5 · asked 5×
- Hill road drainage structures · Transportation Engineering I, chapter 5 · asked 4×
- Water logging remedies and surface drainage in Terai · Irrigation and Drainage Engineering, chapter 9
- Internal/external drainage; water logging; Terai surface drainage · Irrigation and Drainage Engineering, chapter 9
- Types of cross drainage works with sketches · Irrigation and Drainage Engineering, chapter 8 · asked 9×
- Hill climbing and its problems · Artificial Intelligence, chapter 3