Sediment yield, reservoir life and remedies
Short answer
Sediment yield is the total sediment leaving a catchment per unit area per year (t/km²/yr). Reservoir life is the time to fill dead storage, T = C_dead/(η V_s). Remedial measures include catchment treatment, upstream sediment traps, sluicing, flushing, dredging, and design provisions like large dead storage and bottom outlets.
What do you mean by sediment yield and life of a reservoir? Explain various remedial measures that help to reduce reservoir sedimentation.
Sediment yield
Sediment yield is the total quantity of sediment that leaves a catchment and passes a given point (such as a dam site) in a given time. It is expressed as tonnes (or m³) per km² of catchment per year. It depends on rainfall, slope, geology, soil, land cover and land use; in the Himalayan rivers of Nepal it is very high (several thousand t/km²/yr).
Life of a reservoir
The life of a reservoir is the time taken for the sediment to fill the dead (or useful) storage so that the reservoir can no longer serve its purpose:
where is the storage to be filled, is the annual sediment inflow (volume) and is the trap efficiency (Brune's curve; large reservoirs trap more than 90%).
Remedial measures to reduce reservoir sedimentation
- Catchment treatment: afforestation, terracing, contour farming, check dams and gully control, bank protection; avoid unplanned roads and quarrying.
- Upstream sediment traps: silt-trapping dams or small check dams that hold back coarse material before the reservoir.
- Sediment routing in the reservoir:
- Sluicing / bypassing: pass the sediment-laden flood flow through low-level outlets or a bypass tunnel before it settles.
- Venting of density currents through bottom outlets.
- Flushing: draw the reservoir down and open large low-level gates so that high velocity scours the deposits (works best in narrow reservoirs).
- Dredging and mechanical removal of deposits near the intake.
- Design measures: provide large dead storage; place intakes high above the bed; raise the dam if needed; install bottom outlets and sediment excluders.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Remedial measures for sediment deposition in RoR · Hydropower Engineering, chapter 5
- Sediment deposition in storage reservoir; management · Hydropower Engineering, chapter 4
- Remedial measures for slope failure · Soil Mechanics, chapter 11
- In-plane, out-of-plane failure and remedial measures · Concrete Technology and Masonry Structure, chapter 9
- Water logging: causes, effects, remedies · Irrigation and Drainage Engineering, chapter 9 · asked 13×