Communication planning
Short answer
Communication planning determines stakeholder information needs and defines the communication approach. It identifies stakeholders, selects methods and technology, assigns responsibilities, and documents a communication management plan.
What do you mean by communication planning?
Communication planning (Plan Communications Management) is the process of determining the information needs of project stakeholders and defining an approach to communication. It decides who needs what information, when they need it, how it will be given and who will give it. It is closely linked to stakeholder analysis and the project's organisational structure.
Steps
- Identify stakeholders and analyse their communication requirements (stakeholder register).
- Determine information needs: type, format, detail and value of the information.
- Select methods and technology: meetings, email, reports, intranet, video calls; consider urgency, availability, ease of use, project environment and sensitivity.
- Decide frequency and timing: e.g. weekly reports, milestone reviews.
- Assign responsibility for preparing and distributing.
- Decide on feedback and escalation methods.
- Document in the communication management plan and obtain approval.
- Review and update as the project changes.
Inputs, tools and outputs
| Inputs | Tools | Outputs |
|---|---|---|
| Project management plan, stakeholder register, EEF, OPA | Communication requirements analysis, communication technology, models, methods, meetings | Communication management plan, project document updates |
Factors affecting planning
- Number of stakeholders and channels (n(n−1)/2).
- Urgency of information, project size and complexity.
- Team location (co-located or virtual).
- Culture, language and time zones.
- Confidentiality and security needs.
Stakeholders -> Needs -> Methods -> Schedule
-> Responsibilities -> Plan
Importance
Avoids communication overload and gaps, saves time, and allocates resources for communication early.
Example: For a government e-portal project, the plan sets weekly progress emails to the ministry, daily online stand-ups with developers across two cities, and a monthly steering committee meeting.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Project planning matrix (PPM) · ICT Project Management, chapter 7
- Quality planning · ICT Project Management, chapter 10
- Project communication management · ICT Project Management, chapter 11
- Orientation and planning of a building · Building Technology, chapter 1 · asked 12×
- Bar chart vs CPM/PERT as planning tool · Construction Management, chapter 2 · asked 3×
- Planning for business/IT strategies · Information System, chapter 5
- Network planning for remote area telephony · Telecommunications, chapter 1