Cost estimating tools

Short answer

Common tools include analogous (top-down) estimating, parametric modeling, bottom-up estimating, three-point (PERT) estimates, expert judgment, reserve analysis, cost of quality, vendor bid analysis, and project management software.

What are the cost estimating tools?

Cost estimating tools and techniques are the methods used to produce estimates of project costs. The common ones are as follows.

  1. Analogous (top-down) estimating: uses actual cost of a previous similar project as the base. Quick and cheap but less accurate; suitable early.
  2. Parametric modelling: uses statistical relationship between historical data and variables (cost per square metre, cost per function point, COCOMO for software). Accuracy depends on data quality.
  3. Bottom-up estimating: estimate each work package or activity, then sum up the WBS. Accurate but time-consuming.
  4. Three-point estimating (PERT): cost = (optimistic + 4 × most likely + pessimistic)/6.
  5. Expert judgment: input from experienced people or consultants.
  6. Reserve analysis: adds contingency reserve for known risks and management reserve for unknown ones.
  7. Cost of quality: includes prevention, appraisal and failure costs.
  8. Vendor bid analysis: compares bids and quotations from suppliers.
  9. Project management estimating software: spreadsheets, MS Project, simulation and risk tools.
  10. Group decision-making: brainstorming, Delphi technique.
ToolAccuracyEffortStage
AnalogousLowLowConcept
ParametricMediumMediumPlanning
Bottom-upHighHighDetail
Three-pointMediumMediumUncertain tasks
WBS -> Work package estimates (bottom-up)
    -> + Reserves -> Cost baseline

Tips

Use more than one technique, document assumptions, include indirect costs and update estimates.

Example: For a data-centre project, the team uses a parametric rate (Rs per rack), bottom-up estimates for cabling and vendor quotes for servers, then adds 10% contingency.