Estimating process and accuracy

Short answer

The relation is shown by the cone of uncertainty: as the project progresses, more information is available, and accuracy improves. Ranges narrow from ROM (-25%/+75%) through budgetary (-10%/+25%) to definitive (-5%/+10%).

What is the relation between estimating process and accuracy? Explain by sketching the required diagram.

The cost estimating process is progressive: as the project advances, more information becomes available, uncertainty falls and the estimate becomes more accurate. The relationship is described by an estimate accuracy (cone of uncertainty) diagram.

Diagram

 Estimate
 range
 +75% |*
      |   *
 +25% |      *  *  *
 +10% |                *  *  *
    0 |- - - - - - - - - - - - - - - actual cost
  -5% |                *  *  *
 -10% |      *  *  *
 -25% |*  *
      +------------------------------------->
        ROM        Budgetary    Definitive
       (Concept)   (Planning)   (Execution)
                Project progress / time

Simplified form:

Range    Wide ---------------> Narrow
Stage    Concept -> Planning -> Execution
Type     ROM     -> Budget   -> Definitive
Accuracy -25/+75 -> -10/+25  -> -5/+10

Relation

Estimating stageInformation availableAccuracy
ROMLittle: idea, similar projectsVery low (−25% to +75%)
BudgetaryDefined scope, rough designModerate (−10% to +25%)
DefinitiveDetailed WBS, vendor quotesHigh (−5% to +10%)
  • Uncertainty falls as the project progresses: the estimating range narrows with time.
  • Effort versus accuracy: more effort is needed for accurate estimates (detailed WBS, quotes), so accuracy has a cost.
  • Early commitments based on ROM estimates are risky.

Practical lessons

  • Always state the range or accuracy of an estimate.
  • Re-estimate at each phase.
  • Keep higher contingency reserves in early phases.
  • Do not treat early estimates as fixed budgets.

Example: A mobile app initially estimated at Rs 5-9 lakh (ROM) ends with a definitive estimate of Rs 6.5 lakh after the prototype and requirements are signed off.