Skip to main content

Milestones

Short answer

A milestone is a zero-duration event marking a significant deliverable or phase completion, used for progress tracking and status communication. They are specific, measurable, and typically named with a noun and past participle, like 'Design approved'.

What do you mean by milestones?

A milestone is a significant point or event in a project, usually marking the completion of a major deliverable or phase, or an important decision. It has zero duration and consumes no resources. The schedule shows milestones to indicate progress.

Characteristics

  • Zero duration; no work or cost.
  • Specific, observable and measurable (done or not done).
  • Linked to a deliverable, approval or decision.
  • Named with a noun and past participle: "Design approved".
  • Should be few and meaningful, not every task.

Uses

  1. Tracking progress: easy check of whether the project is on schedule.
  2. Communication: summarise status to senior management and customer.
  3. Control points: phase-end reviews (stage gates) decide whether to continue.
  4. Dividing large projects into manageable parts.
  5. Linking payments to the contractor, e.g. 20% on prototype acceptance.
  6. Coordinating with other projects and dependencies.
  7. Motivating the team by giving short-term goals.

Milestone chart example

MilestonePlanned date
Project charter signedWeek 0
Requirements approvedWeek 4
Design completeWeek 8
Prototype demonstratedWeek 14
System testing completeWeek 20
Go-liveWeek 24
Weeks:  0    4    8    14   20   24
        <>   <>   <>   <>   <>   <>

(Diamonds show milestones on a Gantt chart.)

Good practice

  • Make milestones SMART and tie to acceptance criteria.
  • Avoid too many or too few.
  • Maintain a milestone list in the project plan.
  • Track slipping milestones early.

Example: In a network installation project, "Cabling complete" and "Network tested" are milestones, while "pull cables" is an activity.

✓ Answer checked by Claude Opus 5.5 (high effort)

All ICT Project Management chapter 8 questions →