PERT with example
Short answer
PERT is a probabilistic network technique using three time estimates (optimistic, most likely, pessimistic) to compute expected duration and variance. For the example with activities A, B, C in series, expected project time = 12 days, standard deviation = 1.83 days, and probability of finishing within 14 days is about 86%.
What is PERT? Discuss with an example.
PERT (Programme Evaluation and Review Technique) is a probabilistic network technique for planning and controlling projects in which activity times are uncertain. Each activity has three estimates: optimistic time , most likely time and pessimistic time . Times are assumed to follow a beta distribution.
For the project, the critical path is found with values, the expected duration is the sum of on the path, and the project variance is the sum of the variances of the critical activities.
Example
A project has three activities in series.
| Activity | Variance | |||||
|---|---|---|---|---|---|---|
| A | 2 | 4 | 6 | 4.00 | 0.67 | 0.44 |
| B | 3 | 5 | 13 | 6.00 | 1.67 | 2.78 |
| C | 1 | 2 | 3 | 2.00 | 0.33 | 0.11 |
Expected project time days. Project variance , so days.
Probability of finishing in 14 days: , so (86.4 %) from the normal table.
Answer: expected time 12 days, SD 1.83 days, probability of completion in 14 days 86 %.