PERT with example

Short answer

PERT is a probabilistic network technique using three time estimates (optimistic, most likely, pessimistic) to compute expected duration and variance. For the example with activities A, B, C in series, expected project time = 12 days, standard deviation = 1.83 days, and probability of finishing within 14 days is about 86%.

What is PERT? Discuss with an example.

PERT (Programme Evaluation and Review Technique) is a probabilistic network technique for planning and controlling projects in which activity times are uncertain. Each activity has three estimates: optimistic time tot_o, most likely time tmt_m and pessimistic time tpt_p. Times are assumed to follow a beta distribution.

te=to+4tm+tp6,σ=tp−to6,Variance=σ2t_e = \frac{t_o + 4t_m + t_p}{6}, \qquad \sigma = \frac{t_p - t_o}{6}, \qquad \text{Variance} = \sigma^2

For the project, the critical path is found with tet_e values, the expected duration is the sum of tet_e on the path, and the project variance is the sum of the variances of the critical activities.

Example

A project has three activities in series.

Activitytot_otmt_mtpt_ptet_eσ\sigmaVariance
A2464.000.670.44
B35136.001.672.78
C1232.000.330.11

Expected project time =4+6+2=12= 4 + 6 + 2 = 12 days. Project variance =0.444+2.778+0.111=3.333= 0.444 + 2.778 + 0.111 = 3.333, so σP=3.333=1.83\sigma_P = \sqrt{3.333} = 1.83 days.

Probability of finishing in 14 days: Z=14−121.826=1.095≈1.10Z = \dfrac{14 - 12}{1.826} = 1.095 \approx 1.10, so P≈0.864P \approx 0.864 (86.4 %) from the normal table.

Answer: expected time 12 days, SD 1.83 days, probability of completion in 14 days ≈\approx 86 %.