Project types and task environment elements

Short answer

A project is a temporary endeavor to create a unique result within constraints. Labour-intensive uses human labour (e.g., rural road); capital-intensive uses machines (e.g., dam); joint venture shares risk/profit (e.g., Khimti I); multilateral is funded by multiple nations (e.g., ADB project). Task environment includes client, funders, suppliers, contractors, unions, government, community, competitors, users.

Define project. Elaborate labour intensive, capital intensive, joint venture and multilateral projects. Explain the various elements of task environment.

Project

A project is a temporary endeavour, with a definite start and end, undertaken by a team to create a unique product, service or result within limited time, cost and quality constraints. Examples: building the Kathmandu-Terai Fast Track, a 100 MW hydropower plant, a bridge, or developing a hospital information system.

Types of projects

BasisLabour intensiveCapital intensive
Main inputHuman labourMachines and money
EmploymentHighLow
Capital costLowHigh
Speed and qualitySlower, variable qualityFaster, uniform quality
Suitable whereLabour is cheap and plentifulLabour is scarce or the work is large and technical
ExampleRural road by hand, canal digging, trail improvementHydropower dam, tunnel, airport, steel plant
  • Bilateral project: financed or implemented under an agreement between two countries (a donor government and the recipient government). Example: Pokhara International Airport (loan from China Exim Bank), or roads built with Indian grant assistance.
  • Multilateral project: financed by several countries through an international agency. Example: projects funded by the World Bank, ADB or UN agencies, such as the Kathmandu Valley Water Supply improvement.
  • Joint venture project: two or more parties (companies, or a company and the government, often foreign and local) share capital, risk, management and profit. Example: Khimti I hydropower (Himal Power Ltd, with Norwegian and Nepali partners), Upper Bhote Koshi hydropower, and joint venture banks such as Nabil Bank.

Elements of the task environment

The task environment is the part of the external environment that directly interacts with the project.

ElementRole
Client / ownerDefines requirements, pays, approves
Funding agenciesBanks, donors; provide money with conditions
SuppliersMaterials, equipment, services
Contractors and consultantsExecute and supervise the work
Labour and unionsSupply and affect workforce availability
Government agenciesLicences, regulations, taxes, approvals
Local communityLand, acceptance, local labour
CompetitorsCompete for resources and market
Users / customersFinal beneficiaries of the output