Skip to main content

Techniques of project formulation

Short answer

Project formulation uses feasibility analysis, techno-economic analysis, project design and network analysis, input analysis, financial analysis, social cost-benefit analysis, environmental analysis, socio-economic survey, SWOT, sensitivity and risk analysis, and logical framework. These techniques together produce a project report with terms of reference, design basis, cost estimate and indicators.

Describe the different techniques (methods) of project formulation.

Project formulation is the process of developing a project idea into a detailed plan by defining objectives, scope, technical design, cost, benefits and implementation arrangements, so that it can be appraised and implemented.

Techniques of project formulation

TechniqueDescription
Feasibility analysisChecks that the project is possible technically, economically, financially, environmentally and socially
Techno-economic analysisSelects technology, capacity, location and layout, and estimates demand, cost and market potential to screen the options
Project design and network analysisDefines the activities, their sequence and timing (WBS, network, CPM/PERT) and the resources each needs
Input analysisStudies the resources needed: materials, manpower, equipment, utilities, finance, and their availability and cost
Financial analysisCost, funding, cash flow, profitability
Social cost-benefit analysis (SCBA)Compares all costs and benefits to society in monetary terms (B/C ratio, NPV, IRR)
Pre-investment appraisalFinal review of all the above analyses before funds are committed
Environmental analysisImpacts and mitigation (IEE/EIA)
Socio-economic surveyEffects on people, participation
SWOT analysisStrengths, weaknesses, opportunities and threats
Sensitivity and risk analysisEffect of changes in cost, benefit or time on viability
Logical framework / ToR preparationStructures objectives, outputs, indicators and assumptions

The techniques are used together; the output is a project report with ToR, design basis, cost estimate and indicators for decision.