- 2079 Jestha · 2+2 marks
Planned vs unplanned maintenance; maintenance plan
Short answer
Planned maintenance is scheduled in advance, lower cost, short downtime, and safer; examples are annual painting and crack sealing. Unplanned maintenance is triggered by breakdown or emergency, with higher cost and long sudden downtime; examples are burst pipe repair or flood-damaged road repair. A good plan requires inventory, priorities, schedule, resources, records, and regular review.
Differentiate between planned and unplanned maintenance with suitable examples. How can a good maintenance plan be formulated? Explain in brief.
Difference
| Point | Planned maintenance | Unplanned maintenance |
|---|---|---|
| Meaning | Work organised and scheduled in advance | Work done without prior planning, when a need suddenly arises |
| Trigger | Schedule, inspection, condition | Breakdown, failure or emergency |
| Cost | Lower and predictable | Higher, unpredictable |
| Downtime | Short and arranged | Long and sudden |
| Safety | Better | Risk of accidents |
| Examples | Annual painting, cleaning water tank, servicing lift, resealing road cracks | Repair of a burst pipe, collapsed wall, damaged road after flood |
Formulating a good maintenance plan
- Inventory and survey: list all components, with their age, condition and importance (roof, walls, services, drainage).
- Set objectives and standards for performance, safety and appearance.
- Identify tasks and frequencies: daily, monthly, annual and periodic, from manufacturers' manuals and experience.
- Prioritise by safety, risk and cost; critical items first.
- Estimate resources: materials, labour, tools, spare parts, contractors and budget.
- Prepare a schedule (calendar or bar chart) and assign responsibility.
- Implement by work orders; supervise quality and safety.
- Keep records: history cards, inspection reports, costs.
- Review and update the plan regularly using feedback and performance data.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Planned maintenance, planning and scheduling · Construction Management, chapter 9 · asked 2×
- Preventive, corrective and breakdown maintenance · Construction Management, chapter 9 · asked 3×
- Maintenance vs rehabilitation; flexible failure causes · Transportation Engineering II, chapter 4
- GOS vs blocking probability; E.164 plan · Telecommunications, chapter 6
- TPQM and quality-related maintenance · Industrial Engineering and Management, chapter 7
- Software maintenance and fixing common bugs · Instrumentation II, chapter 9