Turn-key contract
Short answer
A turnkey contract is a single contract where the contractor handles design, procurement, construction, and commissioning, delivering a complete facility at a fixed lump-sum price and date. The client simply turns the key; the contractor bears most risks, providing price and time certainty with less client control.
Explain the Turn-key contract.
A turnkey contract is one in which a single contractor is responsible for the entire project (design, procurement of materials and equipment, construction, testing and commissioning) and hands over the complete, ready-to-use facility to the client on a fixed date, at a fixed lump sum price. The client only has to "turn the key" to start using it.
Client -- needs & performance specs -->
Contractor: Design -> Procure -> Build -> Test
-> Hand over (ready)
Features
- One point of responsibility for design and construction.
- Lump sum price; the client gives the performance requirements.
- The contractor takes most of the risk (design, delay, cost).
Merits
Single contract and responsibility; faster delivery through overlapping design and construction; price and time certainty; less management work for the client.
Demerits
The client has less control over design and quality; the scope is difficult to change; the contractor may cut quality to save money; the price includes a high contingency; a clear performance specification is needed; fewer bidders are capable.
Use
Industrial plants, hydropower electro-mechanical works, hospitals, hotels, and large buildings where the client lacks technical staff.