Types of contract

Short answer

Contract types include lump sum, item rate, percentage rate, cost plus (reimbursable), turnkey/EPC, BOT/BOOT, labour, management, joint venture and subcontract. Reimbursable contracts pay actual cost plus a fee, used when scope is uncertain. In Nepal, item-rate contracts are commonest, lump sum for small defined works, and EPC/BOOT for hydropower.

Name and explain the different types of contract (including reimbursable contracts) used in construction, and those practicable in our context.

A contract is a legally enforceable agreement between the client and the contractor to carry out work for a price. Contracts are classified by the method of payment:

TypeDescription
Lump sum (fixed price)Fixed total price for the full defined work; payment as per milestones; risk is on the contractor
Item rate (unit rate / BOQ)The contractor quotes a rate for each item; payment by measured quantity x rate; common for public works in Nepal
Percentage rateThe contractor quotes a percentage above or below the engineer's estimate
Cost plus (reimbursable)The client reimburses actual cost plus a fee
Turnkey / EPC / Design-buildOne contractor designs, procures and constructs; the client gets the ready facility
BOT / BOOT / BOO / BTOThe contractor finances, builds and operates (and may own) for a period
Labour contractOnly labour is supplied by the contractor
Management contract / construction managementThe management contractor manages the trade contractors for a fee
Joint venture / subcontractSeveral firms combine, or part of the work is let to others

Reimbursable (cost-plus) contracts

The client pays the actual cost of labour, materials and equipment plus a fee. Variants:

  1. Cost plus percentage fee: fee = a percentage of cost (the contractor has little incentive to save).
  2. Cost plus fixed fee: the fee is fixed regardless of cost.
  3. Cost plus incentive fee: the saving or overrun is shared.
  4. Cost plus guaranteed maximum price (GMP). Used where the scope is uncertain, urgent, or complex (emergency repair, research facilities). Needs strong audit.

Practicable in Nepal

The item-rate (unit price) contract is the commonest for building, road and irrigation works under the Public Procurement Act and Regulation. Lump sum is used for small and clearly defined works; design-and-build and EPC are used in hydropower; BOOT/BOT for large hydropower under independent power producer (IPP) arrangements; and percentage-rate contracts are used by local bodies for small works.