Lost calls are blocked calls when all trunks busy; Grade of Service (GoS) is the fraction lost in the busy hour. With 600 offered calls, 40 lost, average holding 120 s, traffic offered = 20 E, carried = 18.67 E, lost = 1.33 E, GoS = 0.0667, congestion duration = 240 s.

Define lost calls and grade of service in telephone traffic engineering. During a busy hour, 600 calls were offered to a group of trunks and 40 calls were lost. If the average call duration was 120 seconds, find the traffic offered, carried traffic, lost traffic, GoS and duration of congestion.

Lost calls and grade of service

  • Lost call: a call attempt that cannot be connected because all servers (trunks/switch paths) are busy; in a loss system it is cleared and not served.
  • Grade of Service (GoS): the proportion of calls lost in the busy hour, GoS=calls lostcalls offered=AlAoGoS = \dfrac{\text{calls lost}}{\text{calls offered}} = \dfrac{A_l}{A_o}. A lower GoS means better service (e.g. 0.01 = 1 call in 100 lost).

Given: calls offered Co=600C_o = 600, calls lost Cl=40C_l = 40, mean holding time h=120 s=130h = 120\ \text{s} = \tfrac{1}{30} h, period T = 1 h.

Traffic in Erlangs =calls×hT= \dfrac{\text{calls} \times h}{T}.

(a) Traffic offered

Ao=Co hT=600×130=20 E\begin{aligned} A_o &= \frac{C_o\,h}{T} = 600 \times \tfrac{1}{30} \\ &= 20\ \text{E} \end{aligned}

(b) Traffic carried

Calls carried =600−40=560= 600 - 40 = 560

Ac=560×130=18.67 E\begin{aligned} A_c &= 560 \times \tfrac{1}{30} = 18.67\ \text{E} \end{aligned}

(c) Traffic lost

Al=Ao−Ac=40×130=1.33 E\begin{aligned} A_l &= A_o - A_c = 40 \times \tfrac{1}{30} = 1.33\ \text{E} \end{aligned}

(d) Grade of service

GoS=ClCo=40600=0.0667\begin{aligned} GoS &= \frac{C_l}{C_o} = \frac{40}{600} = 0.0667 \end{aligned}

(e) Duration of congestion

For pure-chance (Poisson) traffic the proportion of time all trunks are busy (time congestion) equals the proportion of calls lost (call congestion), so congestion time in the busy hour is

Tc=GoS×3600 s=40600×3600=240 s\begin{aligned} T_c &= GoS \times 3600\ \text{s} = \frac{40}{600} \times 3600 \\ &= 240\ \text{s} \end{aligned}

Answer: offered traffic = 20 E, carried traffic = 18.67 E (= 18 2/3 E), lost traffic = 1.33 E, GoS = 0.0667 (about 1 in 15), congestion duration = 240 s = 4 min.