- 2080 Chaitra · 4 marks
Limestone reserve for cement factory
Short answer
From apparent dips 1:16 S15°E and 1:22 S27°W, true dip 3.58° towards S16.4°E. True thickness = 215 cos3.58° = 214.6 m. Area 3.27 km × 72.05 m yields volume 5.06×10⁷ m³; with density 2.75×10³ kg/m³, reserve = 1.39×10¹¹ kg (139 million tonnes).
Apparent dip amounts of limestone bed rock along S15°E and S27°W are 1:16 and 1:22 respectively. The vertical thickness of bedrock is 215 m. Calculate the reserve of limestone for cement factory. The extension of the rock having terrain of 3.27 km and 72.05 m. Assume density of limestone is 2.75×10³ kg/m³.
Step 1: true dip from the two apparent dips
Apparent dips: 1:16 along S15°E (bearing 165°) and 1:22 along S27°W (bearing 207°).
Solving: , .
Dip direction (S16.4°E).
Step 2: true thickness
Step 3: volume
The extent of the rock is read as 3.27 km 72.05 m (length width in plan):
Step 4: mass (reserve in tonnes)
Answer: true dip = 3.58° (1:16) towards S16.4°E; true thickness = 214.6 m; volume = 5.06 × 10⁷ m³; reserve of limestone = 1.39 × 10¹¹ kg (about 139 million tonnes).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Reserve: limestone dip 30, apparent 20 m · Engineering Geology II, chapter 7
- Reserve: quartzite apparent dips 1:9 and 1:12, 2.7 x 3.1 km · Engineering Geology II, chapter 7 · asked 2×
- Reserve: quartzite apparent dips 1:9 and 1:12, 4.6 km2 · Engineering Geology II, chapter 7 · asked 2×
- True thickness: limestone vertical 600 m · Engineering Geology II, chapter 7
- True dip from two apparent dips · Engineering Geology II, chapter 6
- True thickness from apparent thickness 210 m · Engineering Geology II, chapter 6
- Strike of limestone bed, dip N40°W, 64° · Engineering Geology I, chapter 5
- Strike of limestone bed directed N20°E, dip 45° · Engineering Geology I, chapter 5
- Strike of limestone bedrock dipping N31°W · Engineering Geology I, chapter 5
- Calculating apparent dip from true dip · Engineering Geology I, chapter 5 · asked 2×