Reserve: quartzite apparent dips 1:9 and 1:12, 4.6 km2
Short answer
True dip 6.35° (1:9.0) N23.5°E, true thickness 104.4 m. For area 4.6 km², reserve = 4.6×10⁶ m² × 104.4 m = 4.80×10⁸ m³ (0.480 km³).
Apparent dip amounts of quartzite bed rock along N20°E and N65°E are 1:9 and 1:12 respectively. The vertical thickness of bedrock is 105 m. Calculate the reserve of construction material for an engineering project at an area of 4.6 km² rock quarry site.
Step 1: true dip from the two apparent dips
For a direction of bearing the gradient of the bed satisfies (, = east and north components of the true gradient).
Solving: , .
Dip direction (N23.5°E).
Step 2: true thickness
Step 3: volume (reserve)
Area
Answer: true dip = 6.35° (1:9.0) towards N23.5°E; true thickness = 104.4 m; reserve = 4.80 × 10⁸ m³ (0.480 km³).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Reserve: quartzite apparent dips 1:9 and 1:12, 2.7 x 3.1 km · Engineering Geology II, chapter 7 · asked 2×
- Reserve: quartzite 400 m, 537 km2 · Engineering Geology II, chapter 7
- True dip from two apparent dips · Engineering Geology II, chapter 6
- Aggregate reserve: quartzite 300 m, 437 km2 · Engineering Geology II, chapter 7 · asked 2×
- Reserve: limestone dip 30, apparent 20 m · Engineering Geology II, chapter 7
- Limestone reserve for cement factory · Engineering Geology II, chapter 7
- Strike of quartzite bed, dip 70° towards S20°E · Engineering Geology I, chapter 5
- Strike of limestone bed directed N20°E, dip 45° · Engineering Geology I, chapter 5
- Strike of quartzite bed, dip 80° towards N10°E · Engineering Geology I, chapter 5