- 2082 Kartik · 4+4 marks
Siphon with 90 mm pipe, number and length
Short answer
Using the summit pressure limit, each 90 mm pipe carries 0.02253 m³/s; three pipelines are required. The total pipe length needed is 42.4 m.
Water from a main canal is siphoned to a branch canal over an embankment by means of wrought iron pipe of 90 mm diameter. The length of pipe up to summit is 25 m, height of summit above main canal is 2 m and the water pressure at the summit is equal to 20 kN/m² absolute. Water surface elevation in the branch canal is 10 m below that of main canal and assume friction factor as 0.03 and consider minor losses. (i) If total quantity of water required to be conveyed is 0.06 m³/s, how many pipelines are needed? (ii) What is the total length of the pipe needed?
Data. m, m (up to the summit), summit 2 m above the main canal, kN/m² absolute, level difference m, , m³/s. Minor losses: entrance and exit . Atmospheric pressure is taken as 101.3 kPa, i.e. m of water.
(i) Number of pipelines
Absolute pressure head at the summit: m.
Energy equation from the main canal surface to the summit (velocity head at the summit, entrance loss and friction over 25 m):
Discharge per pipe: m³/s l/s.
(ii) Total length of pipe
For the same velocity, the total head of 10 m between the canal surfaces is used up in the entrance, friction over the full length and exit:
So the length beyond the summit is m.
Answer: (i) 3 pipelines; (ii) total pipe length m.
✓ Answer checked by Claude Sonnet 5.5
Related questions
- Siphon from main canal to branch canal · Hydraulics, chapter 2 · asked 2×
- Siphon with 75 mm pipes and summit height · Hydraulics, chapter 2
- Branch diameters equal to a 450 mm direct pipe · Hydraulics, chapter 3
- Pipe over hill with cavitation limit · Hydraulics, chapter 2
- Pressure to drive oil up inclined pipe · Hydraulics, chapter 1
- Sarda fall for Bagmati branch canal, Q 25 · Irrigation and Drainage Engineering, chapter 7
- Water hammer in elastic cast-iron pipe · Hydro Power, chapter 1