- 2069 Bhadra · 6 marks
Hydro and thermal power sources
Short answer
Hydropower uses water head and flow to drive a turbine (P=ηρgQH), with free fuel, high efficiency (85-90%), low running cost, but high capital. Thermal power burns fuel to produce steam for a turbine (Rankine cycle), with lower efficiency (30-40%), high fuel cost, pollution, and slow start.
Describe in brief hydro and thermal power sources with basic principles of electricity generation and major features.
Hydropower
Principle: Water stored at a height has potential energy. It flows through a penstock to a turbine, which turns an alternator. Power:
where = flow (m³/s), = net head (m), = overall efficiency.
Dam/Intake -> Headrace -> Surge tank -> Penstock
-> Turbine --[Generator]--> Tx -> Grid
-> Tailrace -> River
Major features
- Fuel is free; very low running cost; renewable and non-polluting.
- High efficiency (85–90 %) and long life (50+ years).
- Quick start and load change: useful for peak load and frequency control.
- High initial cost and long construction time; site depends on geography; often far from load centres.
- Output varies with season (run-of-river plants drop in dry season).
- Examples: Kali Gandaki A (144 MW), Upper Tamakoshi (456 MW).
Thermal (steam) power
Principle: Fuel (coal, oil, gas) is burned in a boiler; the heat turns water into high-pressure steam, which expands in a steam turbine coupled to an alternator, then is condensed and pumped back (Rankine cycle). Chemical energy → heat → mechanical → electrical energy.
Fuel -> [Boiler] -> steam -> [Turbine]--[Gen]-> Grid
^ |
[Feed pump] <- [Condenser] <- cooling water
Major features
- Lower initial cost and shorter construction; can be built near loads or fuel source.
- High running cost due to fuel; overall efficiency only 30–40 %.
- Pollution: CO₂, SO₂, NOx, ash; needs chimneys, precipitators and ash disposal.
- Needs large amounts of cooling water.
- Slow start; best for base load.
| Feature | Hydro | Thermal |
|---|---|---|
| Fuel cost | Nil | High |
| Efficiency | 85–90 % | 30–40 % |
| Capital cost | High | Lower |
| Pollution | Very low | High |
| Starting | Quick | Slow |
| Load type | Base and peak | Base |
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Major electricity sources and sustainability · Power System Analysis I, chapter 1
- Conventional sources and features of a station · Power System Analysis I, chapter 1
- Major components of a power station and functions · Power System Analysis I, chapter 1
- Major components of a power station · Power System Analysis I, chapter 1 · asked 2×
- Basic structure of power system · Power System Analysis I, chapter 1
- Two sources via 0 - j5 Ω: power flow · Power System Analysis I, chapter 3
- Power sources and hydro versus thermal · Hydro Power, chapter 3
- Quarterly progress report: hydro-electricity supply centre (memo) · Communication English, chapter 7
- Energy sources and solar power generation · Power Plant Design, chapter 1
- Thermal, hydro and solar PV plants compared · Power Plant Design, chapter 1 · asked 8×