Title page: Proposal for establishing a sophisticated computer lab at Techno Solutions Pvt. Ltd., submitted to Managing Director. Technical section: 40 workstations, servers, gigabit LAN, UPS, software, security, 11-week schedule. Cost estimate totals Rs. 70,87,500 including contingency.

Imagine that you are requested to submit a proposal for establishing a sophisticated computer lab in one of the technical companies. Write title page, technical section and cost estimate of the proposal that you are going to submit.

Title page

                         PROPOSAL

ESTABLISHMENT OF A SOPHISTICATED COMPUTER LAB AT TECHNO
SOLUTIONS PVT. LTD.

Submitted to:
The Managing Director
Techno Solutions Pvt. Ltd., Kathmandu

Submitted by:
Er. Nabin Shrestha
IT Consultant
Digital Systems Consultancy, Lalitpur

10 November 2026

Technical section

The lab will serve 40 users for software development, testing and training.

  1. Hardware. Forty workstations (Intel Core i7, 16 GB RAM, 512 GB SSD, 24-inch monitor) and two rack servers for file sharing, version control and test environments.
  2. Network. Gigabit LAN using Cat-6 cable and 24-port managed switches, a firewall, and a 200 Mbps fibre internet connection with a backup line. Wi-Fi access points will cover the lab.
  3. Power and cooling. A 10 kVA online UPS and an inverter for at least 2 hours of backup, with two air-conditioners to protect the equipment.
  4. Software. Licensed operating system, office tools, IDEs, database software and antivirus. Open source tools will be used wherever suitable.
  5. Security. Role-based user accounts, daily backups, CCTV and biometric entry.
  6. Implementation. (a) Site survey and design - 2 weeks; (b) purchase - 4 weeks; (c) cabling and installation - 3 weeks; (d) testing and staff training - 2 weeks. The lab will be ready in about 11 weeks.

Cost estimate

S.N.ItemAmount (Rs.)
1Server (rack type) with 3-year warranty, 2 units7,00,000
2Workstations (i7, 16 GB RAM, SSD), 40 units36,00,000
3Network switches, cabling and Wi-Fi access points6,50,000
4UPS, 10 kVA, and inverter4,50,000
5Projector, whiteboard and furniture5,00,000
6Licensed software (OS, office, development tools)3,50,000
7Installation, training and air-conditioning5,00,000
Sub-total67,50,000
Contingency (5%)3,37,500
Grand total70,87,500

The estimate does not include annual maintenance, which is about 8 percent of the equipment cost.