- 2069 Chaitra · 6 marks
Intensity-duration curve and depth-area curve
Short answer
Intensity-Duration curve shows maximum average rainfall intensity decreasing with increasing duration; derived from a storm's mass curve for design. Depth-Area curve shows average storm depth decreasing with area, obtained from isohyetal maps, used to convert point rainfall to areal estimates for large catchments.
Explain Intensity Duration Curve and Depth Area Curve.
Intensity-Duration Curve
It shows how the maximum average rainfall intensity of a storm changes with duration. The intensity is high for short durations and falls for long durations.
- Prepared from a recorded storm: for each duration the greatest rainfall in any period of length is found from the mass curve, and .
- Plotted as intensity (y) against duration (x). With frequency (return period) added it becomes the IDF curve.
i
|*
| *
| *
| *
+--------------- D
Uses: design storm for drainage, culverts, small dams and rational method calculations.
Depth-Area Curve
It shows how the average depth of rainfall of a storm decreases as the area increases. Rainfall is greatest at the storm centre and falls off outward.
- Prepared from an isohyetal map: the average depth inside each isohyet and the area enclosed are computed, and plotted as depth (y) against area (x). Curves for different durations form the DAD curve.
Depth
|*
| *
| *
| *
+--------------- Area
Uses: to convert point rainfall to areal rainfall (areal reduction), design of large catchments, estimating probable maximum precipitation (PMP).
✓ Answer checked by Claude Sonnet 5.5
Related questions
- Intensity-duration curve from storm record · Engineering Hydrology, chapter 2
- Hyetograph and intensity-duration curve, 6:00-12:00 storm · Engineering Hydrology, chapter 2
- Intensity-duration graph from mass curve ordinates · Engineering Hydrology, chapter 2
- Hyetograph and intensity-duration curve, Lumle tipping bucket · Engineering Hydrology, chapter 2
- Mass curve, hyetograph, depth-duration curve · Engineering Hydrology, chapter 2
- DAD curve procedure and isohyetal area data · Engineering Hydrology, chapter 2
- Traffic intensity, GOS and call duration probability · Telecommunications, chapter 6
- Flow duration curve and its applicability · Power Plant Design, chapter 3 · asked 3×
- Hydrograph and flow duration curve · Power Plant Design, chapter 3 · asked 3×
- Power duration curve and primary/secondary energy · Hydro Power, chapter 3