- 2071 Chaitra · 6+3+5 marks
2-hr UH from sketch, net rain 5 in/hr
Short answer
For 5 in/hr for2hr, net rain is10 in, so peak discharge =10×600 =6000 cfs. Total direct runoff equals rainfall depth,10 in. For 0.5 in/hr for4 hr, net rain 2 in gives two 1-in blocks; at 8 p.m. (t=4 hr) Q =400+400=800 cfs.
A 2-hr unit hydrograph for a basin is shown in the sketch.
[Figure: 2-hr unit hydrograph, discharge (cfs) versus time (hr), t = 0 to 9. The curve rises from 0 at t = 0, passes about 200 cfs near t = 1 and 400 cfs near t = 2, peaks at 600 cfs at t = 3, then falls through about 400 cfs near t = 4 and 200 cfs near t = 5, and tails off to near zero by about t = 9. Note: in = inches; 12 inches = 1 feet; cfs = cubic feet/sec; a unit hydrograph is the response of catchment due to 1 inch effective rainfall over it.]
(a) Determine the peak discharge (in cfs) for a net rain of 5.00 in./hr and a duration of 2 hr. (b) What is the total direct surface runoff (in inches) for the storm described in part (a)? (c) A different storm with a net rain of 0.50 in./hr lasts for 4 hr. What is the discharge at 8 p.m. if the rainfall started at 4 p.m.?
A 2-hr UH gives the response to 1 inch of net rain in 2 hr (intensity 0.5 in/hr). Ordinates are directly proportional to the net rain depth, and responses of successive blocks are added with a time lag (principle of proportionality and superposition).
Read from the sketch (t, hr: Q, cfs): 0: 0; 1: 200; 2: 400; 3: 600 (peak); 4: 400; 5: 200; tail to about 0 at 9.
(a) Peak discharge for 5.00 in/hr for 2 hr
Duration is the same as the UH duration (2 hr), so just scale.
Answer: 6000 cfs (at t = 3 hr).
(b) Total direct surface runoff
Direct runoff depth equals net (effective) rain depth.
Answer: 10 inches over the basin.
(c) Storm of 0.50 in/hr for 4 hr, discharge at 8 p.m.
Net rain is 0.5 × 4 = 2 in, which is two successive 2-hr blocks of 0.5 in/hr × 2 hr = 1 in each. Each block gives one UH (multiplier 1); the second is lagged by 2 hr.
Rain starts at 4 p.m., so 8 p.m. is t = 4 hr:
Answer: 800 cfs at 8 p.m.
✓ Answer checked by Claude Sonnet 5.5
Related questions
- 2-hr UH from figure: area, flood, Tc, two storms · Engineering Hydrology, chapter 5
- Direct runoff hydrograph analysis, 4250-acre basin · Engineering Hydrology, chapter 5
- S-curve: 2-hr hydrograph from 4-hr UH · Engineering Hydrology, chapter 5
- Rainfall, lag time and time of concentration from hydrograph · Engineering Hydrology, chapter 5
- Storm hydrograph from 6-h UH, 3-hr storm · Engineering Hydrology, chapter 5 · asked 2×
- 2-hr UH and flood hydrograph from storm · Engineering Hydrology, chapter 5
- Flow net discharge, 200 cc/day · Soil Mechanics, chapter 7
- Unit and mortar for 200 x 400 column · Concrete Technology and Masonry Structure, chapter 8
- Vertical curve 200 m, +1.50% then -2.5% · Surveying II, chapter 6
- Checking whether root locus passes through point P · Control Systems, chapter 5