G-S uses iterative substitution one bus at a time, linear convergence, many iterations. N-R uses Jacobian and Taylor series, quadratic convergence, few iterations, better for large systems. Decoupled load flow assumptions: X>>R, small angle differences, so P-δ and Q-|V| problems can be solved separately.

How G-S method is different from N-R method for the load flow analysis? Write down the assumptions are to be made for decoupled load flow analysis.

Difference between G-S and N-R methods

PointGauss–SeidelNewton–Raphson
PrincipleIterative substitution, one bus at a timeTaylor series linearisation using Jacobian
VariablesComplex voltages (rectangular)∣V∣\lvert V\rvert and δ\delta (polar)
ConvergenceLinear, slowQuadratic, fast
IterationsMany; grow with system size3–5; nearly independent of size
Time per iterationSmallLarge (Jacobian formed and solved)
MemoryLowHigher
Acceleration factorNeededNot needed
ReliabilityMay diverge in ill-conditioned systemsReliable
Suitable forSmall systemsLarge systems

Assumptions for decoupled load flow

  1. Transmission lines have high X/R ratio, so Gik≪BikG_{ik} \ll B_{ik}.
  2. Voltage angle differences between connected buses are small: sin⁡(δi−δk)≈0\sin(\delta_i - \delta_k) \approx 0, cos⁡(δi−δk)≈1\cos(\delta_i - \delta_k) \approx 1.
  3. Hence ∂P/∂∣V∣≈0\partial P/\partial|V| \approx 0 and ∂Q/∂δ≈0\partial Q/\partial\delta \approx 0, so the P–δ and Q–V problems are solved separately: ΔP=J1Δδ\Delta P = J_1\Delta\delta, ΔQ=J4Δ∣V∣\Delta Q = J_4\Delta|V|.