Short answer

The grid iron system interconnects mains and branches in loops, eliminating dead ends. It provides reliable supply, uniform pressure, and good firefighting flow, but requires complex design and higher cost, and is unsuitable for irregularly grown towns.

With a neat sketch, discuss the grid iron system of water distribution including its advantages and disadvantages.

The grid iron (reticulation) system is a layout in which the mains, sub-mains and branches are interconnected in a rectangular grid, so that every pipe is fed from at least two directions and there are no dead ends.

  Main (from reservoir)
   ||====+======+======+=====
   ||    |      |      |
   ||====+======+======+=====   sub-mains
   ||    |      |      |
   ||====+======+======+=====   branches
   Valves at every junction

Description

  • The main runs along the principal road, sub-mains branch off it at right angles, and branches connect the sub-mains. Pipes meet at junctions to form loops.
  • Suitable for well planned, regularly laid out towns with a rectangular road pattern.
  • Design is done by loop methods such as Hardy-Cross because flow can reach a point by more than one path.

Advantages

  1. Water reaches any point from two or more sides, so there is no stagnation and quality is good.
  2. If one pipe is closed for repair, the rest of the area still gets water (only a short section is cut off by sectional valves).
  3. Pressure is more uniform and losses are lower, because the flow divides between several paths.
  4. Good discharge for firefighting from several directions.
  5. Easy to extend the network.

Disadvantages

  1. Design is difficult and needs trial-and-error methods (Hardy-Cross) or software.
  2. More pipe length and many valves are needed, so the cost is high.
  3. Many cross-connections, so it is hard to find the leaks and the burst section.
  4. Not suited to irregular, haphazardly grown towns.
  5. Needs skilled laying and maintenance.