Rapid sand filter for 60000 population

Short answer

Design flow 8262 m³/d. Four beds, each 3.9 m × 4.9 m, total depth 3.4 m. Filter media: 0.7 m sand (effective size 0.5 mm, UC ≤1.5) over 0.45 m graded gravel. Underdrain: 550 mm manifold with 32 laterals of 75 mm, perforated with 507 holes (12 mm dia) per bed.

Design rapid sand filter for a population of 60000 nos for a newly growing urban area.

Population 60,000 is taken as the design population for the new urban area. Per capita demand is assumed to be 135 lpcd (urban supply as per Nepal Water Supply Design Guidelines).

Step 1: Design flow

  • Design population = 60,000 (given)
  • Average daily demand Q=60,000×135/1000=8,100Q = 60,000 \times 135/1000 = 8,100 m³/day
  • Add 2% for wash water: Q′=1.02×8,100=8,262Q' = 1.02 \times 8,100 = 8,262 m³/day, i.e. 344.2 m³/h (plant works 24 h/day)

Step 2: Plan area and number of beds

  • Filtration rate adopted = 4.5 m³/m²/h (4500 L/h/m², usual range 3000–6000)
  • Total area A=344.2/4.5=76.5A = 344.2/4.5 = 76.5 m²
  • Number of beds N=1.22QMLD=1.228.10N = 1.22\sqrt{Q_{MLD}} = 1.22\sqrt{8.10} = 3.47, adopt 4 beds (minimum 4 so that one can be washed while the rest work)
  • Area of one bed =76.5/4=19.12= 76.5/4 = 19.12 m²
  • Take L/B=1.25L/B = 1.25: B=19.12/1.25=3.91B = \sqrt{19.12/1.25} = 3.91 m. Adopt B = 3.9 m, L = 4.9 m (area 19.11 m² each, total 76.44 m²)
  • Actual rate with all beds working = 4.50 m/h; with one bed under wash = 6.00 m/h (within 3–6 m/h, OK)

Step 3: Filter media (sand and gravel)

LayerSizeDepth
Filter sandeffective size 0.5 mm, UC ≤ 1.5700 mm
Gravel layer 4 (top)3–6 mm100 mm
Gravel layer 36–12 mm100 mm
Gravel layer 212–20 mm100 mm
Gravel layer 1 (bottom)20–40 mm150 mm

Gravel (base material) is 450 mm in total. It supports the sand, stops it entering the laterals and spreads the wash water evenly.

Step 4: Underdrainage (perforated manifold and laterals)

  • Backwash rate = 0.6 m³/min/m² (0.01 m/s) for 10 min, so wash flow per bed =0.01×19.11=0.191= 0.01 \times 19.11 = 0.191 m³/s
  • Total perforation area = 0.3% of bed area =0.003×19.11=0.057= 0.003 \times 19.11 = 0.057 m²
  • Perforation diameter 12 mm (area 1.131 cm²): number of holes =507= 507 per bed
  • Manifold along the 4.9 m length, laterals at 0.3 m c/c on both sides: 4.9/0.3≈164.9/0.3 \approx 16 per side, i.e. 32 laterals, about 16 holes each
  • Area of laterals = 2 × perforation area =0.115= 0.115 m², i.e. 0.115/32=0.00360.115/32 = 0.0036 m² each, so D=68D = 68 mm, adopt 75 mm; length ≈(3.9−0.55)/2=1.68\approx (3.9 - 0.55)/2 = 1.68 m (L/D ≈ 22, below 60, OK)
  • Area of manifold = 2 × area of laterals =0.229= 0.229 m², so D=540D = 540 mm, adopt 550 mm
  • Wash velocity in manifold =0.191/0.229=0.83= 0.191/0.229 = 0.83 m/s (< 2.5 m/s, OK)

Step 5: Depth of the bed

Free board 0.5 m + water depth over sand 1.5 m + sand 0.7 m + gravel 0.45 m + underdrain space 0.25 m = 3.4 m.

 Inlet  ->  | Free board 0.5 m         |
            |~~~ water 1.5 m ~~~~~~~~~~|--> wash-water
            |__________________________|    trough
            | Sand 0.7 m               |
            | Gravel 0.45 m            |
            |___o_o_o_laterals_o_o_o___|
            |====== manifold ==========|--> filtered
            (3.4 m total depth)          water

Answer: 4 rapid sand filter beds, each 3.9 m × 4.9 m, 3.4 m deep, filtration rate 4.5 m/h, sand 0.7 m on 0.45 m graded gravel, with a perforated underdrain of a 550 mm manifold and 32 laterals of 75 mm.