Construction joints in structure

Short answer

A construction joint is a planned stop in concreting, placed where shear and bending are minimal. In slabs and beams, it is in the middle third of the span; in columns, at the top of footing and 75 mm below the beam soffit. Joining involves cleaning and roughening the old surface, wetting, applying a bonding coat, using shear keys or dowels, and placing new concrete.

What is construction joint in the structure? Illustrate the positions of construction joints in beam, column and slab. Describe the methods of joining new concrete to old one in the structure.

Construction joint

A construction joint is made where concrete placing is stopped and resumed after the earlier concrete has set, because the structure cannot be cast in a single operation. It must be located where shear and bending are small, and it must give good bond between old and new concrete.

Positions of construction joints

Positions (IS 456 / IS 11817):

  • Slabs: in the middle third of the span, at right angles to the main reinforcement.
  • Beams: in the middle third of the span (where secondary beams frame into girders, the joint in the girder is offset by at least twice the width of the secondary beam).
  • Columns: at the top of the footing, and about 75 mm below the lowest beam/slab soffit (or below the haunch/capital).
  • Walls: at openings, at junctions, and in the middle third.
  Slab/beam                 Column
  ___________|___________    |slab|
  |<-L/3->|joint|<-L/3->|    | beam
                             | col  ---- joint just below beam
                            ===footing=== joint at top of footing

Methods of joining new concrete to old concrete

  1. Cleaning: remove all loose material and laitance from the old concrete, and roughen the surface by hacking, wire brushing or sand blasting to expose the aggregate.
  2. Wetting: saturate the old surface with water for several hours, and remove the free water before concreting.
  3. Bonding coat: apply a layer of neat cement slurry or 10-15 mm of rich cement mortar (1:2) just before placing the new concrete.
  4. Bonding agent: apply an epoxy or latex (SBR) bonding agent for better adhesion.
  5. Shear keys or dowels: form a groove (key) in the old concrete or fix dowel bars across the joint for load transfer.
  6. Placing new concrete: place it in layers, compact it thoroughly with a vibrator, and cure it well.
  7. Waterstops (PVC or rubber strips) in water-retaining structures.