Chapter 10 · 2 hours
Causes and prevention of cracks in buildings
IOE past exam questions
Past questions and answers
13 questions set from this chapter, 7 of them more than once; 3 are most repeated (set, or a close variant set, in 3 or more exams). Most repeated first.
- Most repeated · 4 of 32 exams
- Asked 4 times
- 2079 Asoj · 4 marks
- 2078 Poush · 4 marks
- 2076 Bhadra · 4 marks
- 2072 Magh · 8 marks
Write short notes on structural and non-structural cracks in the building.
Answer
Structural cracks
Structural cracks occur from faults in design, construction or loading that affect the strength and stability of the structure. They are wide, progressive and often pass through the full thickness.
- Causes: overloading, differential foundation settlement, poor design or detailing, shear and bending failure, corrosion of reinforcement, earthquake, defective materials.
- Appearance: diagonal or step cracks near supports, vertical cracks in the middle of beams, cracks near column-beam joints, cracks at the soffit of slabs.
- Danger: may cause collapse. They need immediate investigation and repair.
Non-structural cracks
Non-structural cracks come from internal stresses in building materials. They do not affect the strength directly but allow water entry and look bad.
- Causes: shrinkage, thermal expansion, moisture movement, chemical reaction, poor curing, vegetation.
- Appearance: fine, hairline, random (map) cracks, in plaster, floors and walls.
- Remedy: cement slurry or sealant, fresh plaster, expansion joints.
| Point | Structural | Non-structural |
|---|---|---|
| Cause | Loads, settlement, design faults | Shrinkage, temperature, moisture |
| Width | Wide, growing | Narrow, usually stable |
| Danger | Affects stability | Affects appearance, durability |
| Repair | Strengthening, grouting, jacketing | Filling, plaster |
- Most repeated · 3 of 32 exams
- Asked 3 times
- 2079 Chaitra · 4 marks
- 2079 Jestha · 4 marks
- 2070 Bhadra · 8 marks
Explain the methods of repairing (remedial methods for) different types of cracks in building.
Answer
Cracks are repaired by the method that suits their type, width and cause. The cause (such as settlement) should be removed first.
Repair by crack width
| Crack width | Remedy |
|---|---|
| Hairline (< 0.3 mm) | Fill with cement slurry or paint-grade filler; fresh plaster |
| Small (0.3-1.0 mm) | Rake out, fill with cement-sand mortar (1:3) or polymer-modified mortar |
| Medium (1-3 mm) | Epoxy injection or cement grout through packers |
| Wide (> 3 mm) | Remove and rebuild, stitching with steel clamps, epoxy mortar, jacketing |
| Foundation settlement | Underpinning, grouting, soil improvement |
| RCC cracks | Epoxy injection, grouting, jacketing, bonding steel plates |
| Roof cracks | Waterproof treatment, expansion joints, sealants |
Methods in brief
- Surface sealing: hairline cracks are filled with cement slurry or polymer-modified paste.
- Raking and filling: crack is widened into a V groove (10-20 mm), cleaned, and filled with cement-sand mortar 1:3 or epoxy mortar.
- Epoxy injection: low-viscosity epoxy is injected through packers fixed along the crack; used for structural cracks in RCC.
- Grouting: cement or chemical grout pumped into wide cracks and voids.
- Stitching: U-shaped metal clamps fixed across the crack and embedded in epoxy or mortar.
- Jacketing / section enlargement: extra concrete cover with new reinforcement on columns and beams.
- Bonding steel plates or FRP on the tension face.
- Underpinning or soil improvement for settlement cracks.
- Re-plastering with chicken mesh over joints between different materials.
- Expansion joints / sealants for thermal cracks.
- Most repeated · 3 of 32 exams
- Asked 3 times
- 2074 Bhadra · 4 marks
- 2072 Asoj · 4 marks
- 2071 Magh · 8 marks
What are the main causes of cracks in a building?
Answer
A crack is a visible separation in a wall, slab, plaster or any building element. Cracks can be structural or non-structural. The main causes are as follows.
| Cause | How it cracks the building |
|---|---|
| Moisture movement | Bricks, blocks and concrete expand on wetting and shrink on drying; mortar and plaster shrinkage |
| Thermal movement | Expansion and contraction with temperature in roofs, long walls, parapets |
| Settlement of foundation | Unequal settlement due to poor or non-uniform soil, wrong foundation level, change in moisture, or inadequate depth |
| Elastic deformation | Overload, deflection of beams and slabs, bending and shear |
| Corrosion of reinforcement | Rust expands and splits the concrete cover |
| Chemical action | Sulphate attack, alkali-aggregate reaction, carbonation |
| Vegetation | Roots of trees near walls and foundations |
| Earthquake and wind | Lateral forces on weak walls and joints |
| Poor workmanship and materials | Poor curing, mix, bonding, early removal of formwork, missing joints |
| Overloading and design error | Excess load, wrong detailing |
| Fire, vibration | Heat damage, machine vibration |
Prevention
- Proper investigation and design of foundation for uniform settlement.
- Provide expansion, contraction and construction joints.
- Use good materials and proper mortar mix; cure at least 7 days.
- Allow lintels and bands (plinth, lintel, roof band).
- Protect reinforcement with enough cover.
- Remove vegetation near the foundation.
- Waterproofing the roof and walls.
- Asked 2 times
- 2078 Chaitra · 4 marks
- 2077 Chaitra · 4 marks
Write down the causes of cracks that occur in a building and its remedial measures briefly.
Answer
Cracks in buildings arise from the following causes.
| Cause | How it cracks the building |
|---|---|
| Moisture movement | Bricks, blocks and concrete expand on wetting and shrink on drying; mortar and plaster shrinkage |
| Thermal movement | Expansion and contraction with temperature in roofs, long walls, parapets |
| Settlement of foundation | Unequal settlement due to poor or non-uniform soil, wrong foundation level, change in moisture, or inadequate depth |
| Elastic deformation | Overload, deflection of beams and slabs, bending and shear |
| Corrosion of reinforcement | Rust expands and splits the concrete cover |
| Chemical action | Sulphate attack, alkali-aggregate reaction, carbonation |
| Vegetation | Roots of trees near walls and foundations |
| Earthquake and wind | Lateral forces on weak walls and joints |
| Poor workmanship and materials | Poor curing, mix, bonding, early removal of formwork, missing joints |
| Overloading and design error | Excess load, wrong detailing |
| Fire, vibration | Heat damage, machine vibration |
Remedial measures
| Crack width | Remedy |
|---|---|
| Hairline (< 0.3 mm) | Fill with cement slurry or paint-grade filler; fresh plaster |
| Small (0.3-1.0 mm) | Rake out, fill with cement-sand mortar (1:3) or polymer-modified mortar |
| Medium (1-3 mm) | Epoxy injection or cement grout through packers |
| Wide (> 3 mm) | Remove and rebuild, stitching with steel clamps, epoxy mortar, jacketing |
| Foundation settlement | Underpinning, grouting, soil improvement |
| RCC cracks | Epoxy injection, grouting, jacketing, bonding steel plates |
| Roof cracks | Waterproof treatment, expansion joints, sealants |
Additional measures: provide movement joints, good drainage, proper curing, tie beams, and good-quality materials.
- Asked 2 times
- 2070 Chaitra (old course) · 4+4 marks
- 2068 Baisakh (old course) · 2+2+4 marks
Why are joints necessary (important) in building construction? Briefly explain the expansion joint in a building with necessary sketches.
Answer
Why joints are necessary
Buildings change in size because of temperature and moisture, and settle unevenly. Without joints, these movements create stresses that crack the structure. Joints are provided:
- To allow expansion and contraction due to temperature changes.
- To permit shrinkage movement of concrete and masonry.
- To allow differential settlement of different parts.
- To control the location of cracks.
- To limit the size of pours of concrete (construction joints).
- To separate parts with different heights or loads.
Expansion joint
Expansion joint: a gap of 20-25 mm, provided through the full depth of the structure above the foundation to allow expansion and contraction due to temperature, so that cracks do not form. Used at intervals of 30-45 m in buildings, in long walls, slabs, roofs and parapets.
Expansion joint in a wall/slab
slab | 25 mm gap | slab
=====| |=====
wall | filler | wall
| (bitumen) |
| sealant on top
foundation continuous below
The gap is filled with a compressible filler (bitumen-impregnated fibre board, cork, rubber) and sealed on top with sealant. The two parts are fully separated, often by a double column or wall.
- Asked 2 times
- 2066 Bhadra (old course) · 16 marks
- 2065 Shrawan (old course) · 4 marks
Why are joints necessary in the building structures? Describe in detail the types of joints in structures and their uses.
Answer
Why joints are necessary
Buildings are exposed to temperature changes, moisture, shrinkage, settlement and earthquake movement. Joints give space for these movements, so that the structure does not crack. Joints also make casting in stages possible.
Types of joints and their uses
1. Expansion joint Expansion joint: a gap of 20-25 mm, provided through the full depth of the structure above the foundation to allow expansion and contraction due to temperature, so that cracks do not form. Used at intervals of 30-45 m in buildings, in long walls, slabs, roofs and parapets.
Expansion joint in a wall/slab
slab | 25 mm gap | slab
=====| |=====
wall | filler | wall
| (bitumen) |
| sealant on top
foundation continuous below
The gap is filled with a compressible filler (bitumen-impregnated fibre board, cork, rubber) and sealed on top with sealant. The two parts are fully separated, often by a double column or wall.
2. Construction joint Construction joint: a joint made where concrete placing is stopped and resumed after it has set, because the structure cannot be cast in a single operation. It must be located where shear and bending are small and must provide good bonding.
Positions (as per IS 456):
- Slabs: at the middle third of span, parallel to the main reinforcement.
- Beams: at the middle third of span (also at secondary beams and girders: at a distance of twice beam width from the main beam).
- Columns: at the top of the footing, and just below the beam/slab soffit (or below the haunch/capital).
- Walls: at openings, at the junctions, and in the middle third.
Slab/beam Column
___________|___________ |slab|
|<-L/3->|joint|<-L/3->| | beam
| col ---- joint just below beam
===footing=== joint at top of footing
3. Contraction (control) joint, sliding joint and settlement joint Contraction (control) joint: a groove cut in the concrete at fixed spacing (e.g. 3-6 m in pavements and floors) so that shrinkage cracks form along the joint line. Sliding joint: allows horizontal movement between a slab and a wall, with a bitumen layer or plain sheets. Settlement (isolation) joint: between parts with different foundations or heights so that settlement does not crack the building.
4. Isolation/separation joint: between a slab and a column or wall, so that each moves independently.
5. Seismic (separation) joint: a wider gap (as per IS 4326 / NBC 105) between adjacent buildings or blocks to prevent pounding in an earthquake.
| Joint | Where used | Purpose |
|---|---|---|
| Expansion | Long walls, slabs, roofs, 30-45 m | Allow thermal expansion |
| Construction | Stopping point of concreting | Allow staged casting |
| Contraction | Floors, pavements, walls | Control shrinkage cracks |
| Sliding | Slab on wall | Horizontal movement |
| Settlement | Different foundation depth | Differential settlement |
| Seismic | Between blocks | Prevent pounding |
- Asked 2 times
- 2066 Jestha (old course) · 2.5 marks
- 2062 Baisakh (old course) · 16 marks
What is construction joint in the structure? Illustrate the positions of construction joints in beam, column and slab. Describe the methods of joining new concrete to old one in the structure.
Answer
Construction joint
Construction joint: a joint made where concrete placing is stopped and resumed after it has set, because the structure cannot be cast in a single operation. It must be located where shear and bending are small and must provide good bonding.
Positions of construction joints
Positions (as per IS 456):
- Slabs: at the middle third of span, parallel to the main reinforcement.
- Beams: at the middle third of span (also at secondary beams and girders: at a distance of twice beam width from the main beam).
- Columns: at the top of the footing, and just below the beam/slab soffit (or below the haunch/capital).
- Walls: at openings, at the junctions, and in the middle third.
Slab/beam Column
___________|___________ |slab|
|<-L/3->|joint|<-L/3->| | beam
| col ---- joint just below beam
===footing=== joint at top of footing
Methods of joining new concrete to old concrete
- Cleaning: remove all loose and laitance material from old concrete, and roughen the surface by hacking, wire brushing or sand blasting to expose the aggregate.
- Wetting: saturate the old surface with water for several hours, and remove the free water before concreting.
- Bonding coat: apply a layer of neat cement slurry or 10-15 mm of rich cement mortar (1:2) just before placing new concrete.
- Bonding agent: apply an epoxy or latex (SBR) bonding agent for better adhesion.
- Shear keys or dowels: form a groove (key) in the old concrete or fix dowel bars across the joint for load transfer.
- Placing new concrete: place in layers and compact thoroughly with a vibrator; cure well.
- Waterstops (PVC or rubber strips) in water-retaining structures.
- 2073 Magh
Differentiate between structural and non-structural cracks and with the help of neat sketches. Write down its causes of occurrence.
Answer
| Point | Structural cracks | Non-structural cracks |
|---|---|---|
| Meaning | Cracks due to faults affecting strength and stability | Cracks due to internal stresses in materials |
| Width | Wide (often > 1 mm), growing | Narrow, hairline, stable |
| Causes | Overloading, settlement, design faults, earthquake, corrosion | Shrinkage, temperature, moisture, poor curing |
| Pattern | Diagonal, step, vertical through thickness | Random, map type, horizontal in plaster |
| Danger | Can cause collapse | Mostly appearance, durability |
| Repair | Epoxy injection, jacketing, underpinning | Cement slurry, filling, new plaster |
Structural (settlement) Non-structural (shrinkage)
_______________ _______________
| \ step crack | | ~~ map cracks |
| \_ | | ~~ |
| \_ wide | | |
|_______\________| |________________|
foundation settles
Causes
Structural: overloading, unequal settlement of foundations, poor design and detailing, shear and bending failure, corrosion of steel, earthquake and wind, early removal of formwork. Non-structural: drying shrinkage of mortar, plaster and concrete, thermal expansion and contraction, moisture movement of bricks, chemical action (sulphate attack), vegetation, poor materials and workmanship.
- 2081 Chaitra · 4 marks
Define crazing. What are the common problems for crack on roof of the building?
Answer
Crazing
Crazing is the formation of a network of fine, shallow, hair-like cracks on the surface of plaster, concrete, paint or glaze, looking like a spider web or map. It is caused by shrinkage of the surface layer due to rapid drying, rich mix, too much trowelling, or sudden temperature change. It affects appearance only and is repaired by filling with cement slurry or repainting.
Common problems of cracks on roofs
- Thermal expansion and contraction of a slab or parapet in sun, causing cracks and leaks.
- Shrinkage cracks in the terrace screed or slab due to poor curing.
- Deflection and overload causing cracks in slabs.
- Corrosion of reinforcement with spalling at the soffit.
- Differential movement of the parapet and slab causing horizontal cracks.
- Poor waterproofing and ponding, giving leakage and dampness.
- Lack of expansion joints in large terraces.
Prevention: good curing, expansion joints, insulation and waterproofing, correct slope, proper reinforcement cover.
- 2080 Chaitra · 4 marks
Explain the causes and preventive measures for the development of horizontal crack in load bearing wall just below the RCC slab.
Answer
A horizontal crack often forms in a load-bearing wall just below the RCC roof slab.
Causes
- Thermal movement: the RCC slab, heated by the sun, expands more than the wall below, and drags the top of the wall outwards. In cooling, it contracts and the wall cracks horizontally.
- Different expansion of concrete and masonry.
- Slab deflection causing rotation at the support and lifting of the wall edges.
- Shrinkage of the slab in the first few months.
- Poor bearing or lack of a sliding layer between slab and wall.
- Moisture movement of the wall below.
------ RCC slab ------> expands
====================== horizontal crack
| brick wall |
Preventive measures
- Provide a sliding joint (bitumen coat with polythene, or two layers of tarred paper) between the slab and the wall top.
- Provide thermal insulation or a reflective finish (lime concrete terracing, white tiles) on the roof.
- Provide a ring beam (roof band) to tie the wall.
- Provide expansion joints in long slabs.
- Use proper curing, good mortar, adequate bearing (at least 150-200 mm).
- Use a soft flexible pad or a bearing plate where the slab ends on the wall.
- 2081 Chaitra · 6 marks
Why retrofitting is necessary? Explain methods of repairing crack of different width.
Answer
Need for retrofitting
Retrofitting is the strengthening of an existing structure to make it safer and serviceable. It is necessary because:
- Many old buildings were built without earthquake-resistant design and may collapse in future earthquakes (as in Nepal 2015).
- Damage from earthquake, fire, corrosion and ageing reduces strength.
- Loads or building use change (extra storeys).
- Design or construction errors are found.
- Codes (NBC 105) have been revised, and retrofitting is cheaper than demolishing.
Repair of cracks by width
| Width | Method |
|---|---|
| Hairline, < 0.3 mm | Surface painting with cement slurry or sealant |
| 0.3 to 1 mm | Rake and fill with cement-sand mortar 1:3, or polymer mortar |
| 1 to 3 mm | Epoxy or cement grout injection through packers at 150-300 mm spacing |
| 3 to 10 mm | Rake into V groove, epoxy mortar, with stitching by clamps |
| > 10 mm | Remove and rebuild the portion; add jackets, bands or mesh; stitching |
General steps: remove the cause (settlement, leakage), clean the crack with compressed air, seal the surface, inject or fill, then cure and finish.
- 2062 Poush (old course)
Describe the joints in the structure. Illustrate the types of joints. Explain briefly the expansion and construction joints and their probable positions in the structure.
Answer
A joint is a planned break or gap in a structure to allow movement or to stop concreting. It reduces random cracking.
Types of joints
- Expansion joint: allows thermal expansion.
- Contraction (control) joint: controls shrinkage cracks.
- Construction joint: at stopping place of concreting.
- Settlement joint: between parts that settle differently.
- Sliding joint: between slab and wall for horizontal movement.
- Seismic joint: between blocks, to avoid pounding.
Expansion joint
Expansion joint: a gap of 20-25 mm, provided through the full depth of the structure above the foundation to allow expansion and contraction due to temperature, so that cracks do not form. Used at intervals of 30-45 m in buildings, in long walls, slabs, roofs and parapets.
Expansion joint in a wall/slab
slab | 25 mm gap | slab
=====| |=====
wall | filler | wall
| (bitumen) |
| sealant on top
foundation continuous below
The gap is filled with a compressible filler (bitumen-impregnated fibre board, cork, rubber) and sealed on top with sealant. The two parts are fully separated, often by a double column or wall.
Positions: at 30-45 m intervals along long buildings; where the plan changes shape (L, T, U); where height or foundation level changes; between wings and old and new portions; in long parapets, roofs, retaining walls and pavements.
Construction joint
Construction joint: a joint made where concrete placing is stopped and resumed after it has set, because the structure cannot be cast in a single operation. It must be located where shear and bending are small and must provide good bonding.
Positions (as per IS 456):
- Slabs: at the middle third of span, parallel to the main reinforcement.
- Beams: at the middle third of span (also at secondary beams and girders: at a distance of twice beam width from the main beam).
- Columns: at the top of the footing, and just below the beam/slab soffit (or below the haunch/capital).
- Walls: at openings, at the junctions, and in the middle third.
Slab/beam Column
___________|___________ |slab|
|<-L/3->|joint|<-L/3->| | beam
| col ---- joint just below beam
===footing=== joint at top of footing
- 2067 Asar (old course) · 2+6 marks
Why is it necessary to provide a joint in building structure (especially cement concrete structure)? Draw a neat freehand sketch of vertical wall section showing expansion joint at foundation, plinth, lintel, floor and roof/terrace level for a typical residential building having 350mm thick brick wall.
Answer
Why joints are necessary
Concrete, brick and other materials expand with a rise of temperature and moisture and contract when cooled or dried (concrete also shrinks while curing). If a long structure is not free to move, tensile and compressive stresses develop and cause cracks. Joints are provided to:
- Allow free thermal expansion and contraction, and shrinkage.
- Prevent cracking, buckling and spalling of walls, slabs and floors.
- Accommodate differential settlement and small movements (a separate joint type for structures with different loads or foundation levels).
- Divide a long or irregular building into independent blocks.
Expansion joint: a full-depth gap (25-40 mm) through the building from roof to plinth, usually at 30-45 m intervals (IS 3414 / IS 456 suggests about 45 m) or where the plan changes shape (L, T, U), or the height changes. The foundation is generally not divided unless settlement difference is expected, but here the joint is carried to the foundation top. Filler (bitumen-impregnated fibre board, cork or expanded polystyrene) is placed in the gap and the surface sealed with a sealant, plus a cover strip (flashing/GI or copper strip).
Sketch: section through a 350 mm brick wall at the expansion joint
Terrace |<-25->| Terrace
==========|filler|========== roof slab (cover strip)
[ beam ] | | [ beam ]
---------| |--------- lintel level
350 wall| |350 wall (double wall, gap)
---------| |--------- floor (sealant+strip)
plinth | | plinth DPC both sides
---------| |---------
footing | | footing (joint to foundation)
Details of the joint at each level
| Level | Detail |
|---|---|
| Foundation | Joint carried to foundation top; separate walls and footings each side (double wall), a gap of 25 mm with filler; sometimes foundation continuous but wall divided |
| Plinth | 25 mm gap with filler (bitumen-impregnated board), sealed with mastic; DPC continuous with flashing |
| Wall (350 mm) | Two separate 175 mm half-thick walls (or two separate walls) with 25 mm gap, tongue-groove avoided; filled with bitumen board |
| Lintel / sunshade | Gap through lintel and chajja, covered with a GI/aluminium flashing |
| Floor | Gap through the floor slab and finish; filled with sealant and covered by brass/aluminium strip |
| Roof / terrace | Gap through slab; expansion joint filler, waterproof membrane, with a U-shaped copper/GI cover or rubber bellows (and a protective brick on edge) |
Good detailing keeps the gap free of mortar and debris and watertight.
Questions from Old Question Collection (CE 652) (IOE exam papers from 2062 to 2079 (23 papers)) and Old Question Collection (CE 652) (IOE exam papers from 2069 to 2081 (19 papers; only the ones not in the first collection are used)). Answers are written for this site; check them against your class notes.
Chapter titles and hours from the IOE syllabus ↗