Keep correct alignment and gradient with sight rails, adequate depth and cover, narrow trench width with working space, consider soil nature, dewater if needed, use shoring for safety, provide barricades, locate existing services, prepare a proper bed, backfill in layers after testing, and dispose spoil suitably.

Explain various factors that should be kept in mind while excavating trenches for pipes.

Factors to be kept in mind when excavating trenches for pipes:

  1. Alignment and gradient: Correct line and slope as in the drawing, set with sight rails and boning rods, so that the pipe drains properly (sewers need a fixed gradient).
  2. Depth: Enough cover over the pipe to protect it from loads (about 1 m for water pipes; below frost and traffic effects), and adequate depth for the gradient.
  3. Width of trench: Pipe diameter plus 300 to 600 mm working space, as narrow as practical to reduce the load on the pipe and the cost.
  4. Nature of soil: Soft soil needs side slopes or shoring; rock needs blasting or chiselling.
  5. Ground water: Dewatering by pumping, sumps or well points.
  6. Side support (shoring): Timber or steel sheeting for deep trenches in loose soil, for the safety of workers.
  7. Safety and traffic: Barricades, signs, lights; spoil kept at least 0.6 to 1 m from the edge.
  8. Existing underground services (cables, pipes) should be located and protected.
  9. Bed preparation: A level trench bottom with a bed of sand or concrete, and joint holes at the sockets.
  10. Backfilling: In layers with compaction, after the pipeline has been tested.
  11. Disposal of excavated material and restoration of the road surface.