Mortar and estimation of mortar requirement
Short answer
Mortar is a workable paste of binder, sand and water for bonding masonry. Estimation: subtract solid brick volume from masonry volume to get wet mortar; dry volume = wet × 1.27. For 1:n mix, cement = dry volume/(1+n) and sand = n × dry volume/(1+n).
What is mortar? Describe the estimation of mortar requirement.
Mortar
Mortar is a paste of binding material (cement or lime), fine aggregate (sand) and water; it is used to join bricks or stones, fill joints and plaster surfaces. Common types are cement mortar (1:3 to 1:6), lime mortar, cement-lime (gauged) mortar and mud mortar.
Estimation of mortar requirement
The mortar needed depends on the volume of masonry and the volume of units in it.
- Find the volume of brickwork (m³).
- Find the size of a brick with mortar, e.g. mm, and the number of bricks .
- Volume of bricks without mortar .
- Wet volume of mortar volume of bricks.
- Dry volume wet volume 1.27 (to account for voids in sand, shrinkage and wastage).
- Divide by the mix ratio : cement , sand .
- Convert cement to bags: 1 bag (50 kg) m³.
Worked example (10 m³ brickwork, 1:6)
- Bricks .
- Brick volume m³.
- Wet mortar m³; dry m³.
- Cement m³ ( 13 bags); sand m³.
For plaster: mortar volume area thickness 1.27 (dry).