Short answer

Use lead compensator when transient is poor but steady state is good; use lag when steady-state error is large but transient is acceptable; use lag-lead when both need improvement. PID is preferred when the plant model is uncertain, on-site tuning is required, or for process plants with slow dynamics or dead time.

Discuss the situations where you prefer phase lag/lead controllers and PID controllers.

Lag/lead compensators and PID controllers both reshape the loop, but each fits a different situation.

Prefer a phase-lead compensator when

  • the system is stable but has a poor transient response (low phase margin, large overshoot, slow rise);
  • you need a higher bandwidth and faster response, and some extra noise sensitivity is acceptable;
  • the plant has an integrator or a double integrator (e.g. satellite or position servo) that needs phase lead to stabilise it.

Prefer a phase-lag compensator when

  • the transient response is already satisfactory but the steady-state error is too large (low KpK_p, KvK_v);
  • low-frequency gain must be raised without changing the crossover frequency much;
  • high-frequency noise must be attenuated, and a slower response is acceptable.

A lag–lead compensator is used when both the transient and the steady-state response must be improved.

Prefer a PID controller when

  • the plant model is not accurately known and the controller must be tuned on site (Ziegler–Nichols rules, for example);
  • zero steady-state error to a step is needed (integral action) together with damping (derivative action);
  • the plant is a process plant (temperature, pressure, flow, level) with slow dynamics or dead time, where PID is the industry standard;
  • the controller must be simple, with three parameters an operator can understand.
SituationPreferred controller
Good steady state, poor transientLead
Good transient, poor steady stateLag
Both poor, model knownLag–lead
Model unknown, tuning in fieldPID
Process plants with dead timePI / PID
Noisy measurementLag or PI (avoid D)