Metrics for control objectives
Short answer
Metrics from step response: rise time (10-90% of final), peak time and overshoot percentage, settling time within a 2-5% band, steady-state error, stability/damping, disturbance rejection, and control effort. A good design has small rise time, minimal overshoot, short settling time, and near-zero steady-state error.
Explain the metrics used to measure control objectives.
Control objectives are measured with a set of performance metrics, mostly from the step response of the closed-loop system:
- Rise time (tr): time for the output to go from 10 % to 90 % of the final value. Measures speed of response.
- Peak time (tp) and overshoot (Mp): tp is the time taken to reach the first (maximum) peak; Mp is the maximum amount, usually in percent, by which the output exceeds the final value: Mp = (peak - final)/final × 100 %.
- Settling time (ts): time after which the output stays within a band (usually 2 % or 5 %) of the final value.
- Steady-state error (ess): final difference between set-point and output: ess = r - y(∞). Measures accuracy.
- Stability / damping: the output must remain bounded and any oscillation must decay (damping ratio, gain and phase margins).
- Disturbance rejection: size and duration of the output change caused by a disturbance.
- Control effort / robustness: size of the actuator output and sensitivity to parameter change.
y
| _ Mp (overshoot)
| ____/ \___ ______ final value (+/-2% band)
| / \/
| /
+--tr--------ts------- t
A good design has small tr, small overshoot, short ts and ess close to zero.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Control methods for interface communication · Embedded System, chapter 5
- Control evaluation steps; PD and PI design · Embedded System, chapter 7
- Budgetary control; objectives, advantages, conditions · Project Engineering, chapter 6
- Traffic engineering objectives; Engset formula · Telecommunications, chapter 6
- True/false: derivative controllers always used with others · Control Systems, chapter 7 · asked 3×
- Road maintenance; gully control measures · Transportation Engineering II, chapter 4