What is MARR; how it is determined
Short answer
MARR is the minimum acceptable rate of return used as the discount rate in project evaluation. It is set based on the weighted average cost of capital, opportunity cost, risk premium, inflation, and capital rationing, with adjustments for project-specific risk.
What is MARR? How do you determine the MARR for a company and project?
What is MARR
The Minimum Attractive Rate of Return (MARR) is the lowest rate of return that a company will accept to invest in a project. A project is accepted only if its IRR (or ERR) ≥ MARR, and the MARR is used as the interest rate in PW, FW, AW and B/C calculations. It is also called the hurdle rate or cut-off rate.
How it is determined
- Cost of capital. MARR must be at least the weighted average cost of capital (WACC): the cost of debt (loan interest, after tax) and the cost of equity (dividend and growth expected by owners), weighted by their share in the capital.
- Opportunity cost. It must not be below the return from the best alternative use of the money (for example, bank fixed deposit, government bonds, or other projects that must be dropped when funds are limited).
- Risk premium. A risk allowance is added: MARR = risk-free rate + risk premium. Risky projects (new product, new technology) get a higher MARR than safe ones (cost reduction, replacement).
- Inflation. The rate should cover expected inflation so that the real return remains positive.
- Capital rationing and policy. When funds are limited, MARR is raised until the accepted projects just use the available budget. Management policy and the investment horizon also affect it.
For a company and for a project
- Company MARR: a single base rate (usually WACC plus a margin) for the whole firm.
- Project MARR: the company rate adjusted for the project's own risk, life and type: MARR(project) = base MARR + project risk premium.
Example: bank loan at 12%, owner expects 18% on own money, 50:50 mix gives WACC = 15%; adding 3% for risk gives MARR = 18%.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Sensitivity of PW to investment and MARR · Engineering Economics, chapter 6 · asked 2×
- IRR evaluation, MARR 20% · Engineering Economics, chapter 3
- ERR with MARR = ε = 10% · Engineering Economics, chapter 3
- Define IRR; find IRR and ERR of project · Engineering Economics, chapter 3 · asked 2×
- Both payback periods, is project acceptable · Engineering Economics, chapter 3
- Modified B/C ratio for 100,000 project · Engineering Economics, chapter 3
- Feasibility using two methods, MARR 15% · Project Engineering, chapter 6
- Joint stock company advantages and limitations · Organization and Management, chapter 4
- Ownership and structure for software company · Organization and Management, chapter 4
- Proposal to start a software company · Communication English, chapter 6