Short answer

Inflate each item by its own rate: sales 5%, labour 8%, materials 0% and 6%, salvage 3%. Discount net actual cash flows at 20%: PW ≈ Rs 9,300. The project is marginally acceptable.

Evaluate the PW of the following project. Initial investment = Rs. 1,00,000 (in constant dollars) Annual sales income = Rs. 40,000 (in constant dollars) Annual labour cost = Rs. 3,000 (in constant dollars) Annual material X = Rs. 2,000 (in constant dollars) Annual material Y = Rs. 1,000 (in constant dollars) Salvage value = 20% of initial investment (in constant dollars) Inflation rate for sales income, labour cost, materials X, material Y and salvage value are 5%, 8%, 0%, 6% and 3% respectively for the project period. Take market interest rate = 20%, project life is 4 years.

Each item inflates at its own rate (differential inflation), so each is converted to actual dollars as constant × (1 + f_item)^n and then all net actual cash flows are discounted at the market interest rate of 20%. The initial investment (year 0) needs no conversion.

Salvage value = 20% × 1,00,000 = 20,000 constant dollars, inflating at 3%: 20,000(1.03)⁴ = 22,510.

ItemConstant $Inflation f
Sales income40,0005%
Labour3,0008%
Material X2,0000%
Material Y1,0006%
Salvage20,0003%
YearSalesLabourMaterial XMaterial YSalvageNet actual CFPW at 20%
142,0003,2402,0001,060035,70029,750
244,1003,4992,0001,124037,47726,026
346,3053,7792,0001,191039,33522,763
448,6204,0812,0001,26222,51063,78630,761

Net actual CF = sales − labour − X − Y + salvage.

PW = −1,00,000 + 29,750 + 26,026 + 22,763 + 30,761
   = Rs 9,300

Answer: PW ≈ Rs 9,300 (positive but small), so the project is just acceptable at the 20% market rate.