- 2068 Jestha · 10 marks
PW and IRR after tax with SL depreciation
Short answer
Straight-line depreciation = Rs 5 million/year; after-tax cash flow = Rs 6.5 million/year. PW at 10% = Rs 0.604 million > 0; IRR = 11.4% > MARR, so the project is acceptable.
A machine costs Rs 20 million with no salvage value. Rs 8 million revenues per year can be gained. Given: useful life = 4 years. Tax rate = 50%, MARR = 10%. Use straight line depreciation method to evaluate (i) PW (ii) IRR.
Data (Rs million): P = 20; S = 0; revenue = 8/yr for N = 4 years; tax rate = 50%; MARR = 10%; straight-line depreciation.
After-tax cash flow
Depreciation = (20 − 0)/4 = 5 per year
Taxable income = 8 − 5 = 3
Tax = 0.50 × 3 = 1.5
ATCF = 8 − 1.5 = 6.5 per year (years 1 to 4)
Cash-flow diagram:
Year 0 1 2 3 4
CF −20 +6.5 +6.5 +6.5 +6.5 (Rs million)
(i) Present worth at 10%
PW = −20 + 6.5(P/A,10%,4) = −20 + 6.5(3.1699) = −20 + 20.604 = Rs 0.604 million
PW > 0, so the project is acceptable.
(ii) IRR (after tax)
Solve −20 + 6.5(P/A,i,4) = 0, i.e. (P/A,i,4) = 20/6.5 = 3.0769.
i = 11%: (P/A,11%,4) = 3.1024 → PW = +0.166
i = 12%: (P/A,12%,4) = 3.0373 → PW = −0.256
IRR = 11% + 1% × 0.166/(0.166 + 0.256) = 11.4%
Answer: After-tax PW = Rs 604,125 (about Rs 0.60 million) and after-tax IRR = 11.4% > MARR = 10%, so the machine is economically acceptable, though the margin is small. (Before tax the project is much better: IRR = 21.9%.)
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- PW of machine with tax at 50% · Engineering Economics, chapter 7
- After-tax cash flow, sinking fund depreciation · Engineering Economics, chapter 7
- MACRS schedule and after-tax IRR by AW · Engineering Economics, chapter 7
- ATCF and IRR with given depreciation schedule · Engineering Economics, chapter 7
- Depreciation and book value by four methods · Engineering Economics, chapter 7
- After-tax cash flow, DDB with switchover · Engineering Economics, chapter 7
- Dividend per ordinary share, 500 shares, tax 20% · Project Engineering, chapter 6
- Value of a 20-year-old building · Construction Management, chapter 13 · asked 2×
- Gumbel design flood, 21 years data, 40-year life · Engineering Hydrology, chapter 6 · asked 3×
- Gumbel flood at given risk, 50-year project life · Engineering Hydrology, chapter 6