Job costing tracks costs per custom order (e.g., construction) using job cost sheets, giving exact per-job profit but requiring heavy clerical work. Process costing averages costs over a period for continuous mass production (e.g., cement), offering simpler records but only average unit cost.
Write a short note on job and process costing.
Costing methods collect the cost of producing goods or services and assign it to units. The method depends on the nature of production.
Job costing
- Used when work is done in separate jobs or orders, each different and to customer specification (building construction, repair workshop, printing, machinery fabrication).
- A job cost sheet is opened for each job. Direct material, direct labour and a share of overhead are charged to it.
- The cost of a job is known only when the job is complete. Profit is found job by job.
- Overhead is applied with a predetermined rate (e.g. per labour hour).
- Advantages: gives exact cost and profit of each job; helps in quotations and control.
- Limitations: clerical work is heavy; costs are known late.
Process costing
- Used when production is continuous, standardised and mass-produced, passing through successive processes (cement, sugar, chemicals, textiles, oil refining).
- Costs are collected process by process for a period, not by order.
- Cost per unit of a process = (total cost of the process − value of scrap) / equivalent output units. The output of one process becomes the input of the next.
- Normal and abnormal losses, scrap, and work-in-progress (via equivalent units) must be accounted for.
- Advantages: simple, cheap records, suits large output.
- Limitations: gives only average cost; individual unit cost is not known.
| Basis | Job costing | Process costing |
|---|---|---|
| Production | Special orders | Continuous, uniform |
| Cost unit | Job | Process/period |
| Cost known | After job completion | At end of period |
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Non-preemptive SJF with P4 arriving · Embedded System, chapter 6 · asked 2×
- Priority and SJF scheduling with P4 and P5 · Embedded System, chapter 6 · asked 2×
- Procedure of preliminary estimate (office building) · Estimating and Costing, chapter 3 · asked 2×