Skip to main content

Most efficient trapezoidal channel (3H:4V)

Short answer

From Manning's equation with V=0.5 m/s, n=0.012, S=1/2000, R=0.139 m, so depth y=2R=0.278 m. For most efficient trapezoid with 3H:4V slopes, bottom width b equals y, so b=0.278 m, carrying Q≈0.068 m³/s.

Calculate dimensions of a most efficient trapezoidal channel section having side slopes 3H:4V with n = 0.012 consider bed slope 1 in 2000 which carries water at a velocity of 0.50 m/s.

For the most efficient trapezoidal section, R=y/2R = y/2 and half the top width equals one sloping side. Velocity is known, so Manning's equation gives RR directly.

Data

Side slope 3H : 4V, so n=3/4=0.75n = 3/4 = 0.75 horizontal per vertical; 1+n2=1.25\sqrt{1+n^2} = 1.25. Manning's nm=0.012n_m = 0.012, S=1/2000S = 1/2000, V=0.5V = 0.5 m/s.

Hydraulic radius from Manning

V=1nmR2/3S1/2R2/3=0.5×0.012(1/2000)1/2=0.0060.02236=0.2683R=0.26831.5=0.1390 m\begin{aligned} V &= \frac{1}{n_m}R^{2/3}S^{1/2} \\ R^{2/3} &= \frac{0.5 \times 0.012}{(1/2000)^{1/2}} = \frac{0.006}{0.02236} = 0.2683 \\ R &= 0.2683^{1.5} = 0.1390\ \text{m} \end{aligned}

Depth and bottom width

y=2R=0.278 mb=2y(1+n2−n)=2×0.278×(1.25−0.75)=0.278 m\begin{aligned} y &= 2R = 0.278\ \text{m} \\ b &= 2y\left(\sqrt{1+n^2} - n\right) = 2 \times 0.278 \times (1.25 - 0.75) = 0.278\ \text{m} \end{aligned}

(With 3H : 4V slopes, b=yb = y.)

Check

A=(0.278+0.75×0.278)×0.278=0.1352A = (0.278 + 0.75 \times 0.278) \times 0.278 = 0.1352 m², P=0.278+2×0.278×1.25=0.973P = 0.278 + 2 \times 0.278 \times 1.25 = 0.973 m, R=0.139R = 0.139 m. Discharge Q=AV=0.1352×0.5=0.0676Q = AV = 0.1352 \times 0.5 = 0.0676 m³/s.

Answer: Depth ≈ 0.278 m, bottom width ≈ 0.278 m (top width ≈ 0.695 m); it carries about 0.068 m³/s at 0.5 m/s. The section is small because the velocity is low and the channel is smooth.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Hydro Power chapter 1 questions →