Gauging site selection and current meter use

Short answer

Select a straight, stable channel with a well-defined control and no backwater effects. Current meter procedure: divide cross-section, measure depth, lower meter to 0.6d (or 0.2d and 0.8d), count revolutions per second, convert to velocity using V=aN+b, then compute discharge by mid-section method.

What factors should be considered in selecting a site for a stream gauging station? Describe briefly the procedure of using a current meter for measuring velocity of stream.

Factors for selecting a stream gauging site

  • Straight reach: about 5–10 times the river width upstream and downstream, with parallel flow lines.
  • Stable channel: bed and banks free from scour, deposition and shifting, so the stage–discharge relation stays constant.
  • Well-defined control (rock bar, rapids or a weir) downstream, giving a unique stage–discharge relation.
  • No backwater effect from confluences, dams or tides; no eddies or dead water.
  • Flow contained in one channel at all stages, without overflow at floods.
  • Adequate depth and velocity for the current meter in the dry season.
  • Easy access in all seasons and safe working (bridge, cableway).
  • Away from tributaries, so the measured flow represents the site of interest (e.g. near the intake for a hydropower project).

Measuring velocity with a current meter

A current meter (cup type or propeller type) has a rotor whose speed of rotation NN is proportional to water velocity. Its calibration equation is V=aN+bV = aN + b.

Procedure:

  1. Stretch a tag line across the river and divide the width into 15–25 segments (each carrying ≤ 10% of flow).
  2. At each vertical, measure the depth yy with a sounding rod or weight.
  3. Lower the meter (wading rod for shallow water; cable, weight and cableway or bridge for deep water) to the required depth:
    • Shallow (< 0.6–1 m): one reading at 0.6y from the surface.
    • Deeper: two readings at 0.2y and 0.8y; mean V=(V0.2+V0.8)/2V = (V_{0.2} + V_{0.8})/2.
  4. Allow the meter to settle, then count the revolutions over a fixed time (40–100 s). NN = revolutions/time.
  5. Convert to velocity with the rating equation, e.g. V=0.51N+0.03V = 0.51N + 0.03.
  6. Compute discharge by the mid-section or mean-section method: Q=∑biyiViQ = \sum b_i y_i V_i.
  tag line  0   1   2   3   4   5
  ~~~~~~~~~~|~~~|~~~|~~~|~~~|~~~|~~~~
   \        o   o   o   o   o      /  o = meter at 0.6y
    \_______o___o___o___o_________/      or 0.2y & 0.8y