How cable size is chosen in an installation
Short answer
Cable size is determined by current rating, voltage drop, and short-circuit withstand. Transformer-MDB is governed by full-load current and fault level; MDB-SDB often by voltage drop over longer runs; SDB-end by load current and motor starting drop. Key factors: load current, derating conditions, voltage drop limit, protective device coordination.
How is the size of cable chosen for electrical installation from transformer to MDB, MDB to SDB and SDB to end use? On what factors does the selection primarily depend?
A cable is sized so that it carries the design current without overheating, keeps voltage drop within limits and withstands short-circuit current. The same method is used for each stage, but the governing condition changes from stage to stage.
Transformer to MDB
- Design current = full-load LT current of the transformer: I = kVA × 1000 / (√3 × 400). Example: 250 kVA → 360.8 A.
- Cable (or parallel runs/bus duct) must carry this current after derating for grouping and temperature; it must also withstand the transformer LT fault current for the clearing time (A ≥ I_sc·√t / k).
- Run is short, so current rating and short-circuit withstand govern; voltage drop is usually small (aim < 1 %).
MDB to SDB
- Design current = maximum demand of the SDB (connected load × Ku × Ks), plus 20–25 % future margin.
- Cable rating ≥ rating of the protective MCCB/MCB at the MDB.
- Feeder lengths are moderate to long, so check voltage drop (about 1.5–2.5 %); long feeders often need a larger size than the current alone requires.
SDB to end use
- Design current of each final circuit: motor full-load current (I = P/(√3·V·η·pf)), lighting or socket circuit current.
- Cable rating ≥ MCB rating; minimum 1.5 mm² Cu for lighting, 2.5–4 mm² for power sockets.
- For motors, check voltage drop during starting (5–7 × FLC) and running.
- Total drop from transformer to the farthest load should be within about 5 %.
Factors on which selection depends
- Load current (design current) and type of load.
- Current-carrying capacity from the manufacturer's table.
- Derating factors: ambient temperature, grouping, method of laying (air, duct, ground), depth and soil resistivity.
- Permissible voltage drop and cable length.
- Short-circuit current and fault clearing time.
- Rating of the protective device (coordination Ib ≤ In ≤ Iz).
- Conductor material (Cu/Al), insulation (PVC/XLPE) and armouring.
- Future load growth and economics (cost of losses).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Cable size MDB to SDB-1 (60 kW) and SDB-2 (75 kW) · Industrial Power Distribution and Illumination, chapter 5 · asked 4×
- Cable size MDB to SDB1 (80 kW) and SDB2 (10 kW) · Industrial Power Distribution and Illumination, chapter 5 · asked 5×
- Cable size MDB to SDB1 (70 kW) and SDB2 (90 kW) · Industrial Power Distribution and Illumination, chapter 5 · asked 5×
- Selecting MCCB and MCB for MDB and SDB · Industrial Power Distribution and Illumination, chapter 5
- Cable and MCB size for two motors (η = pf) · Industrial Power Distribution and Illumination, chapter 5 · asked 2×
- Cable and MCB size for two motors · Industrial Power Distribution and Illumination, chapter 5 · asked 2×
- Electrical characteristics of a unit transformer · Power Plant Design, chapter 4 · asked 2×
All Industrial Power Distribution and Illumination chapter 5 questions →