Short answer
From safe exit gradient 1/6, downstream cutoff depth 6.4 m below floor (198 m), minimum impervious floor length ≈34.2 m between cutoffs.
An irrigation barrage has to be designed to pass a flood of 10,000 m³/s, through alluvium media (median diameter of particles = 0.33 mm). The flood level, pond level and downstream floor level are 207.0 m, 204 m and 198.0 m respectively. If the safe exit gradient is 1/6, compute minimum total impervious floor length required to safeguard the structure from piping. Prepare a conceptual section of the designed structure.
Data and assumptions
m³/s, mm, flood level m, pond level m, d/s floor level m, safe exit gradient . The design head for piping is the static head with no tail water, m. The d/s cutoff is taken to a depth of below the HFL.
1. Silt factor, waterway and scour depth
2. Depth of d/s cutoff
Scour level m. Depth of the d/s pile below the floor:
3. Floor length from the exit gradient
Check: with m is 0.1667 .
Answer: Minimum total impervious floor length (between the end cutoffs) m, with the d/s cutoff 6.4 m deep. If a deeper d/s cutoff (2R) is used, the exit gradient is satisfied for any floor length, and the length is then fixed by the uplift thickness and the jump.
Conceptual section
Flood level 207 ~~~~~~~~~~~~~~~~~~~~~~~
Pond level 204 ~~~~~~~~~|gate|
u/s block apron ___crest__| |__ glacis __ d/s jump floor
====================================================== 198
u/s pile (1.0-1.5R) <--- b = 34.2 m ---> d/s pile 6.4 m
inverted filter + block apron
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Minimum impervious floor length, 11000 m3/s · Irrigation and Drainage Engineering, chapter 5 · asked 2×
- Khosla: barrage HGL and floor thickness · Irrigation and Drainage Engineering, chapter 5
All Irrigation and Drainage Engineering chapter 5 questions →